23 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The ground improvement can best be defined as

the alteration of natural soil compressible property to make it favourable for

design

physically altering the permeability of weak natural soil strata

chemically altering the consolidation properties of highly compressible natural

soil

the improvement of soil engineering properties through physical and chemical

intervention on a natural soil

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the purpose of soil stabilisation in building construction

to increase its compressibility

to reduce permeability and compressibility of the soil

to reduce its shear strength

to enhance its plasticity

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the function of weep holes in a retaining wall?

to reduce the soil pressure

to reduce the water pressure

to reduce the soil and water pressure

to eliminate the soil and water pressure

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the purpose of the counterforts structure to the cantilever wall?

Act as supports to the stem of cantilever walls in load bearing

Act as tension stiffeners to reduce bending and shear stresses of cantilever wall

Act as trusses that connect the stem and base of cantilever wall

Act as an aesthetic value to the cantilever wall

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Grouting Material includes the following EXCEPT

Cement

Bituminous

Bentonite

Water

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Bentonite or clay grouting is used in ground conditions where the particles of the soil are too small for cement grouting.

TRUE

FALSE

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

methods that can be taken to avoid failure of surrounding structures during the excavation works for the proposed project.

CUT OFF WALLING

STRUTTING AND SHORING

UNDERPINNING

ALL OF THE ABOVE

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?