Project Management Introduction Ver1

Project Management Introduction Ver1

Professional Development

10 Qs

quiz-placeholder

Similar activities

Energizer quiz-Recapitulation-Group 3

Energizer quiz-Recapitulation-Group 3

Professional Development

10 Qs

Project Management - Module 1 (PRE-TEST)

Project Management - Module 1 (PRE-TEST)

Professional Development

10 Qs

Subsidery Plan - Assignment

Subsidery Plan - Assignment

Professional Development

7 Qs

Construction Cost Estimating and Analysis Quiz No. 1

Construction Cost Estimating and Analysis Quiz No. 1

Professional Development

10 Qs

Project Management

Project Management

Professional Development

15 Qs

Project Integration Management Quiz

Project Integration Management Quiz

Professional Development

10 Qs

Prevention Vs Correction - Assignment

Prevention Vs Correction - Assignment

Professional Development

7 Qs

Project Management

Project Management

Professional Development

10 Qs

Project Management Introduction Ver1

Project Management Introduction Ver1

Assessment

Quiz

Professional Development

Professional Development

Easy

Created by

Hero Rusyadi

Used 1+ times

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The six competing constraints on a project include:
budget, quality, scope, resources, risk and cost
quality, scope, budget, schedule, resources, time
budget, schedule, scope, quality, resources and risk
budget, scope, cost, quality, resources, risk

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The five project management process groups include:
initiating, planning, executing, monitoring and controlling
integration, scope, time, cost, and quality
initiating, planning, executing, monitoring and controllling, and closing
concept, planning, execution, controlling, and closeout

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The project becomes officially authorized through the:
approval of the concept phase gate
approval of the project charter
approval of the WBS
approval of the scope statement

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Accepted deliverable are an input to which process group
Initiating
Planning
Executing
Closing

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A temporary endeavor that creates a unique product or service is called a:
Project
Plan
Program
Portfolio

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which process involves subdividing project deliverables and project work into smaller, more manageable portions
Develop Schedule
Create WBS
Estimate Activitiy Resources
Define Scope

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which of the following contracts should you use for projects that have a degree of uncertainty and require a large investment early in the project life cycle?

Fixed price

Cost reimbursable

Cost-Plus

Time & Material

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?