2023S Review Questions 2

Quiz
•
Business
•
Professional Development
•
Hard
Lcit Pmguild
Used 1+ times
FREE Resource
30 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Avoid challenging stakeholders.
Make changes to the project schedule in real-time.
Ensure all stakeholders receive the same information.
Establish good working relationships with all stakeholders.
Answer explanation
Relationships between the project manager, the project’s stakeholders, and the project team are very important. The most critical part of stakeholder management is relationships.
2.
MULTIPLE SELECT QUESTION
1 min • 1 pt
Cost
Quality assurance
Schedule
Quality customer service
Quality planning
Answer explanation
Data gathering techniques that can be used but are not limited:
- Brainstorming
- Interviews
- Focus groups
- Questionnaires and surveys
- Benchmarking
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Discuss optional stakeholder representation.
Create a communications management plan.
Set up a project team room.
Hold a project kick-off meeting.
Answer explanation
The stakeholders did not engage in the project because clear expectations were not set, nor were they trained on how the agile methodology works. A skill assessment at the beginning of the project would have helped the project manager understand the level of competency of the stakeholders in this area. Creating Communications Management plan, holding project kick-off meeting & setting up project team room will be the next steps.
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Trust
Transparency
Honesty
Loyalty
Answer explanation
Building relationships with your stakeholders also helps to build trust between you, them, and your project team – and trust around the project. Trust is a key component of effective communication with others. Stakeholders who feel they can trust you are more apt to share information with you and be engaged in the project.
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Fast tracking
Crashing
Resource leveling
Lead and lag
Answer explanation
If the scope increases without increasing the schedule, the crashing technique achieves compression by adding more resources.
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Start developing the project management plan based on a previous project template from the project management office (PMO).
Conduct an impact analysis of the new initiative to determine how the project should be rolled out.
Plan a working session focusing on the scope, vision, and mission of the initiative.
Conduct benchmarking to determine the business viability of the initiative.
Answer explanation
For any project success its critical to initially define vision and mission of the overall initiative even before focusing on detailed planning. Project management plan, determining business viability or impact analysis should be carried out once the initiative is defined properly.
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Create the project charter.
Conduct a kick-off meeting.
Develop the communications management plan.
Prepare and distribute the responsible, accountable, consult, and inform (RACI) matrix.
Answer explanation
PMBOK Sixth Edition Chapter 1 and 3 provide the details for the response to this question. The Project Manager activities may include consulting with executive and business unit leaders on ideas for advancing strategic objectives, improving organizational performance, or meeting customer needs. The project manager may also be called upon to manage or assist in business analysis, business case development, and aspects of portfolio management for a project. A project manager may also be involved in follow-on activities related to realizing business benefits from the project. After this the project manager is supposed to communicate with the stakeholders.
The correct answer to this question, therefore, is: "Conduct a Kick-Off meeting."
The Distractors are well defined and accepted.
Create a free account and access millions of resources
Similar Resources on Wayground
30 questions
Financial Analyst Quiz

Quiz
•
Professional Development
25 questions
Code of Ethics for Professional Accountants

Quiz
•
University - Professi...
30 questions
Time Level 3 Unit 6

Quiz
•
University - Professi...
30 questions
AgileTestPMP

Quiz
•
Professional Development
26 questions
Real Estate Principles Unit 14 multiple choice 1

Quiz
•
Professional Development
25 questions
orientation day 1 knowledge check

Quiz
•
Professional Development
30 questions
Day 1 Quiz - Video Editing for Educators using Premiere

Quiz
•
Professional Development
25 questions
CoE Christmas Quiz

Quiz
•
Professional Development
Popular Resources on Wayground
18 questions
Writing Launch Day 1

Lesson
•
3rd Grade
11 questions
Hallway & Bathroom Expectations

Quiz
•
6th - 8th Grade
11 questions
Standard Response Protocol

Quiz
•
6th - 8th Grade
40 questions
Algebra Review Topics

Quiz
•
9th - 12th Grade
4 questions
Exit Ticket 7/29

Quiz
•
8th Grade
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
19 questions
Handbook Overview

Lesson
•
9th - 12th Grade
20 questions
Subject-Verb Agreement

Quiz
•
9th Grade