PMI 10G

PMI 10G

Professional Development

175 Qs

quiz-placeholder

Similar activities

Part 1 优品教培中心 F3 Test Your Vocab

Part 1 优品教培中心 F3 Test Your Vocab

KG - Professional Development

180 Qs

Vocab TOEFL 2

Vocab TOEFL 2

Professional Development

171 Qs

Grade7-Unit2 (Sports) Büşra Kahraman

Grade7-Unit2 (Sports) Büşra Kahraman

KG - Professional Development

176 Qs

Grade7-Unit10 (Planets) Serdar

Grade7-Unit10 (Planets) Serdar

KG - Professional Development

172 Qs

Fred's Sentence Quiz Number 1

Fred's Sentence Quiz Number 1

Professional Development

178 Qs

Exam Modules 5, 6, and 7. ICPI

Exam Modules 5, 6, and 7. ICPI

Professional Development

180 Qs

Câu hỏi trắc nghiệm tiếng Việt

Câu hỏi trắc nghiệm tiếng Việt

Professional Development

177 Qs

There is/are quiz

There is/are quiz

Professional Development

170 Qs

PMI 10G

PMI 10G

Assessment

Quiz

English

Professional Development

Hard

Created by

Chris Nguyen

FREE Resource

175 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A smartphone manufacturer is re-assessing its product development methods in response to a sharp increase in user complaints. Analysis of the complaints indicates that the users try to use some features in ways that designers did NOT anticipate. Given these findings, which agile practice would most effectively prevent the problem?
Acceptance Test-Driven Development
Smoke Testing
Behavior-Driven Development
Red, green, refactor

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

An agile team is struggling to solve a blocking issue with packaging design. Eventually, they find a solution, but it requires a different product format. What should the team do before further developing the solution?
Create a prototype and demo it to the end customer.
Ask the product owner to approve the change.
Run a cost/benefit analysis to determine its value.
Check if the change is consistent with the product vision.

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A Project Manager has been asked to conduct a risk analysis that is based on a high-level scope. As part of the this analysis, the Project Manager must use expert judgment to prepare a document. Which document-based action is being performed?
Creating the project charter.
Preparing the scope statement document.
Creating a project management plan.
Documenting the risk management plan.

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A Project Manager overhears a conversation in the company's cafeteria. The speaker says that a possible union action will occur within the next two weeks. The Project Manager knows that any union action will affect the project team, and at this stage of the project, any project delays will cause substantial harm to both budget and schedule. Earlier, the probability of a union action was considered minimal. Thus, it was unanticipated. What should the Project Manager do?
Inform relevant stakeholders and update the risk register with the new information.
Ask stakeholders for additional information regarding the likelihood of the union action, then act on what is heard.
Set up an information session for the project team, letting them know of possible disciplinary sanctions for those who participate in the union action.
Meet with union members and the union leader to resolve this conflict.

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Six months into a strategic agile project, company exectives are closely monitoring its progress. The COO expresses his frustration that the last weekly burn-down charts show the projected completion date significantly moving back and forward several times. How can the project manager forecast the completion date with more accuracy and stability?
Ensure upcoming backlog items are elaborated in more detail with the team.
Educate the executive committee on the flexible nature of agile planning.
Plan for variable-size iterations according to story complexity and load.
Reduce frequency of the progress reports sent to senior stakeholders.

6.

MULTIPLE SELECT QUESTION

1 min • 1 pt

The Project Manager shifts to an agile approach for a project with an aggressive go-to-market timeline. The Project Manager needs to revise the stakeholder engagement plan so that it follows agile principles. What should the Project Manager do to meet this need (choose two)?
Design a digital communication system that allows for virtual submission, logging, reviewing, and escalation of issues.
Remove unnecessary layers of management to promote direct communication between the project team and stakeholders.
Modify templates to include product backlog progression and the burndown rate, and encourage use of standups.
Increase the number of formal training workshops to cover all relevant issues for all stakeholders, including the project sponsor and client.

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A high-level manager in an organization would like to use a critical project resource for a new project. Which action should the Project Manager take?
Contact the program manager to resolve the issue.
Request that the high-level manager provides a replacement.
Use the Legitimate form of power to deny the request
Tell the team and reassign that resource's responsibilities to other team members.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?