PMI-ACP 2

Quiz
•
Professional Development
•
Professional Development
•
Medium
Iman Satyagraha
Used 4+ times
FREE Resource
21 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Your agile team working on some project which a lot of things are unknownat this moment. Hence your team decided to use "rolling wave" planning approach. Which statement are true regarding this?
It is an incremental planning in which work in near terms is planned in detailed
It is an iterative planning in which work in near terms is planned in detailed
It is an iterative planning in which work in near terms is planned in high level
It is an incremental planning in which work in near terms is planned in high level
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Due to restructing in client team, there are some changes in personnel as some new members joined your client team. As agile leader, what is your approach to ensure project participation from these new stakeholders now?
Send these new stakeholders the current status of project over an email so that they are aware of the project details
Invite these new stakeholders to planning, retrospective & review meetings
Share the project charter, team charter with the new stakeholders to make them aware of projects and teams
Share the project repository which contains all the project info with new stakeholders
3.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
The law of diminishing marginal returns is applicable to which type of following features?
Must have
Should have
Exciters
Delighters
4.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
"Customer collaboration over contract negotiation" is one of Agile Manifesto. Which of the following agile approaches helps in achieving this value?
Backlog preparation
Daily Standup
Backlog refinement
Agile measurements
Answer explanation
5.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
Team periodically demostrate the working product to product owner and stakeholders. In flow-based agile, when this demostration conducted?
At the end of iterations
At the end of projects
during retrospective
when enough features are accumulated into a set that is coherent
6.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
Which is not recomended practice when splitting large user stories in order to fit an iteration?
Splitting a large story into its constituent tasks
Splitting a large story into smaller stories if the priorities of the smaller stories are different
Splitting stories by separating functional and non functional aspects
Splitting a large story along the boundaries of the data supported by the story
7.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
Agile team has completed 120 features so far and the project SPI is 1.2. What is the number of planned features the team should was supposed to complete?
144
120
100
the figures can not be computed with given data
Create a free account and access millions of resources
Similar Resources on Wayground
20 questions
FSSC version 5

Quiz
•
Professional Development
20 questions
QM quiz Round-1

Quiz
•
Professional Development
19 questions
IB MYP: Service as Action

Quiz
•
Professional Development
16 questions
The Agile Manifesto and Principles

Quiz
•
Professional Development
20 questions
Dashboard Rules

Quiz
•
Professional Development
18 questions
Monday.com Quiz (Sales & Registrars)

Quiz
•
Professional Development
20 questions
All-in-one CAPM/PMP: Chapter 3

Quiz
•
Professional Development
20 questions
digital product/project management

Quiz
•
Professional Development
Popular Resources on Wayground
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
10 questions
Nouns, nouns, nouns

Quiz
•
3rd Grade
10 questions
9/11 Experience and Reflections

Interactive video
•
10th - 12th Grade
25 questions
Multiplication Facts

Quiz
•
5th Grade
11 questions
All about me

Quiz
•
Professional Development
22 questions
Adding Integers

Quiz
•
6th Grade
15 questions
Subtracting Integers

Quiz
•
7th Grade
9 questions
Tips & Tricks

Lesson
•
6th - 8th Grade