PMP Exam 121-180

PMP Exam 121-180

Professional Development

60 Qs

quiz-placeholder

Similar activities

A) phrasal verbs

A) phrasal verbs

12th Grade - Professional Development

57 Qs

Educador Nivel 1 Capacitación sobre los aspectos básicos de Google (Temas 1,2 y 3)

Educador Nivel 1 Capacitación sobre los aspectos básicos de Google (Temas 1,2 y 3)

Professional Development

55 Qs

021122

021122

Professional Development

55 Qs

Tema 2 GD: CC.AA, Provincias y municipios

Tema 2 GD: CC.AA, Provincias y municipios

Professional Development

59 Qs

TRY OUT PPPK

TRY OUT PPPK

Professional Development

65 Qs

OSI Layer

OSI Layer

University - Professional Development

65 Qs

UK Driving Test

UK Driving Test

Professional Development

58 Qs

CIS Microsoft Excel (Review)

CIS Microsoft Excel (Review)

9th Grade - Professional Development

62 Qs

PMP Exam 121-180

PMP Exam 121-180

Assessment

Quiz

Professional Development

Professional Development

Medium

Created by

J Watson

Used 6+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

60 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

You are the project manager and must determine how best to help Robin complete her project tasks for the current iteration. She chose tasks that are impossible for her to finish on her own. You assign Kelly to assist Robin in completing the tasks. Which aspect of emotional intelligence did you just portray towards your team members?
Social awareness by the use of empathy
Relationship management by the use of influence
Self-management by the use of self-control
Self-awareness by the use of self-confidence

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In negotiating project agreements, the project manager should never give in to unreasonable scope, schedule, and/or resources mainly because:
The project team members may be overburdened, and team morale may decline.
The interests of each stakeholder may not be met.
The project scope should always be fixed and defined in the project charter.
The project manager will always be at the losing end.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which option best describes the technique of applying lags and leads to project activities?
It is a method of determining the amount of time a successor activity may be advanced or delayed with respect to a predecessor activity.
It is a method of categorizing dependencies as mandatory, discretionary, internal, or external.
It is a diagramming method that uses arrows and nodes to depict dependency and precedence relationships.
It is a diagramming method that uses arrows and nodes to show only finish-to-start dependencies.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Managing project communication occurs during which project performance domain?
Project Work
Stakeholder
Planning
Team Performance

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which phrase BEST characterizes a program?
a group of projects managed in a coordinated effort
a project that is subdivided into smaller, more manageable components
a set of deliverables that collectively meet a specific project goal
a project that meets a particular objective

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The project manager has made reference to the project charter when a blocker had been encountered to the implementation of the project. A project charter includes all of the following EXCEPT:
Project tasks and activities
Project goals and objectives
Authority of the project and the stakeholders
Roles and responsibilities

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In developing a business case, which element will provide the rationale for the project?
Business need
Project justification
Expected project outcome
Business strategy

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

By signing up, you agree to our Terms of Service & Privacy Policy

Already have an account?