Unit 4 - Graphs and Networks MC from EA

Unit 4 - Graphs and Networks MC from EA

12th Grade

21 Qs

quiz-placeholder

Similar activities

Graph Theory review

Graph Theory review

12th Grade

17 Qs

Graph Theory revision

Graph Theory revision

12th Grade

20 Qs

untitled

untitled

9th - 12th Grade

17 Qs

Graph Transformations

Graph Transformations

10th - 12th Grade

20 Qs

IA5 Review

IA5 Review

12th Grade

19 Qs

Quadratic Transformations STAAR Practice

Quadratic Transformations STAAR Practice

9th - 12th Grade

16 Qs

Math 2 U4L1 Vocab and Transformation

Math 2 U4L1 Vocab and Transformation

9th - 12th Grade

20 Qs

1-31 HW after 4.6a Graphing from SI

1-31 HW after 4.6a Graphing from SI

9th - 12th Grade

16 Qs

Unit 4 - Graphs and Networks MC from EA

Unit 4 - Graphs and Networks MC from EA

Assessment

Quiz

Mathematics

12th Grade

Medium

Created by

Sharon Davidson

Used 5+ times

FREE Resource

21 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Media Image

What is the minimum spanning tree for this network? All the distances are in Km.

22km

12km

14km

3km

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Media Image

Determine the adjacency matrix that represents this graph.

Media Image
Media Image
Media Image
Media Image

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Media Image

The activity times in the project network shown are in days.

The greatest float time for a non-critical activity in this network is

2 days

4 days

5 days

12 days

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which of the following is a planar graph with 5 vertices and 4 faces?

Media Image
Media Image
Media Image
Media Image

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Identify a minimum spanning tree from the diagrams below.

Media Image
Media Image
Media Image
Media Image

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Media Image

The graph has six vertices.

The vertex with the smallest degree is

1

2

3

4

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Media Image

Activities A, B, C, D, E, F, G, H and J must be completed for the project shown in the network. Activity times are in minutes.

The earliest starting time in minutes for Activity J on the network diagram is:

16

15

11

13

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?