Ujian Akhir Manajemen Proyek
Authored by Rina Indrayani
Life Skills
1st Grade
Used 1+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
30 questions
Show all answers
1.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
1. You are managing a software project. Your QA manager tells you that you need to plan to have her team start their test planning activity so that it finishes just before testing begins. But other than that, she says it can start as late in the project as necessary. What’s the relationship between the test planning activity and the testing activity?
Start-to-Start (SS)
Start-to-finish (SF)
Finish-to-Start (FS)
Finish-to-Finish (FF)
2.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
2. Which of the following is NOT a tool or technique used in Estimate Activity Durations?
A. SWAG Estimation
B. Parametric Estimation
C. Analogous Estimation
D. Three-Point Estimation
3.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
3. What’s the correct order og the time management planning processes?
3. What’s the correct order og the time management planning processes?
A. Sequence Activities, Define Activities, Estimate Activity Resources, Estimate Activity Durations, Develop Schedule
B. Define Activities, Sequence Activities, Develop Schedule, Estimate Activity Resources, Estimate Activity Durations
C.
Define Activities,Sequence Activities,Estimate Activity Resources,Estimate Activity Durations, Develop Schedule
D. Develop Schedule, Define Activities, Sequence Activities, , Estimate Activity Resources, Estimate Activity Durations
4.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
4. You’re working on a project that has an EV of $7362 and a PV (BCWS) of $8232 what’s your SV?
4. You’re working on a project that has an EV of $7362 and a PV (BCWS) of $8232 what’s your SV?
A. -$870
B. $870
C. 0.89
D. Not enough information to tell
5.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
5.. You’re on the project selection committee. You’re reviewing a document that describes the strategic value of a potential project and its benefits to the company. What’s this document called?
A. Project Charter
B. Business Case
C.Benefit measurement method
D. Contract
6.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
6. What is the output of Direct and Manage Execution?
A. Approved change requests
B.Project management processes
C.Deliverables
D. Forecasts
7.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
7. Which of the following is NOT an example of operational work?
A.Building a purchase order system for accounts payable
B. Submitting weekly purchase orders through a purchase order system
C. Deploying weekly anti-virus software updates
D. Yearly staff performance evaluations
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Microsoft
or continue with
%20(1).png)
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?