latihan pecahan dan perbandingan

latihan pecahan dan perbandingan

Professional Development

7 Qs

quiz-placeholder

Similar activities

TIU 3 - 25 Oktober 2020

TIU 3 - 25 Oktober 2020

Professional Development

6 Qs

Belajar UP matematika

Belajar UP matematika

Professional Development

10 Qs

kuis FR PART 5

kuis FR PART 5

Professional Development

10 Qs

Materi Perbandingan

Materi Perbandingan

10th Grade - Professional Development

10 Qs

TIU 14

TIU 14

Professional Development

10 Qs

Mencari Jarak dan Waktu

Mencari Jarak dan Waktu

KG - Professional Development

10 Qs

Soal cerita

Soal cerita

University - Professional Development

10 Qs

olympiade matematika SD

olympiade matematika SD

Professional Development

10 Qs

latihan pecahan dan perbandingan

latihan pecahan dan perbandingan

Assessment

Quiz

Mathematics

Professional Development

Hard

Created by

Fatwa Mikail

Used 7+ times

FREE Resource

7 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

D. 1

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Dengan jumlah pekerja sebanyak 12 orang, sebuah proyek dapat diselesaikan selama 15 hari. Agar proyek dapat selesai selama 10 hari, banyak pekerja yang harus ditambahkan adalah . . . .

A. 20

B. 15

C. 6

D. 8

E. 18

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Andi Menyelesaikan Patung 12 hari dan Budi 6 Hari. Jika Mereka Bekerja Bersama, Berapa Hari Patung Selesai?

a. 3 hari

b. 6 hari

c. 4 hari

d. 12 hari

5.

MULTIPLE CHOICE QUESTION

1 min • 5 pts

Media Image

?

A

B

C

D

E

6.

MULTIPLE CHOICE QUESTION

1 min • 5 pts

Media Image

?

A

B

C

D

E

7.

MULTIPLE CHOICE QUESTION

15 mins • 1 pt

Dalam 10 jam seseorang dapat menjahit 4 kemeja. Waktu yang diperlukan untuk menjahit 6 kemeja adalah … jam.

12

15

18

20