2023S Review Questions 4

Quiz
•
Business
•
Professional Development
•
Hard
Lcit Pmguild
FREE Resource
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Answer explanation
To understand how the project aligns with the organization's strategy, the stakeholder needs to evaluate the goals, objectives, benefits and risk to see how they compare to the organizations goals and risk tolerance. The cost, schedule, risks and WBS provides details on the project activities, but not the detail to compare to the overall strategy. Likewise, the benefits, effort and resources, or schedule, benefits, and WBS would not provide enough detail to compare to the strategy.
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Answer explanation
The question notes the necessary resources are working on another project, indicating that it is a shared resource in either a functional or matrix type organization where the functional manager is the person who is able to reschedule, reassign or replace resources. Negotiate a solution with the functional manager and project sponsor would be the case in this type of organization structure. Outsource the resource necessary to address the risk may be a potential outcome, however not until the discussion is held with the functional manager and project sponsor. Modify the project schedule has no relevance to the question and the issue at hand. Meet with project sponsor to request additional resources and schedule delay, may be a potential outcome, however not until the discussion is held with the functional manager and project sponsor.
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Answer explanation
Scope creep can be avoided or minimized by defining a specific scope baseline and adhering to the agreed upon change control process.
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Answer explanation
As per the new ECO task 1.7: Address and remove impediments, obstacles, and blockers for the team. This also falls into the servant leadership role a PM needs to have in Agile and hybrid environments. As a top priority, the need for the Project Manager is to remove the obstacles and blockers. The other answer choices are incorrect. Documentation is not a priority in Agile hybrid environments, hence adding blockers to the issue log and creating risk management plan can be done as a secondary step and hence is not the correct answer. The scenario described in the question does not indicate that the stakeholders are communicating with the team directly, hence this choice is not the correct answer.
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Answer explanation
Sponsor approval is required for changes to the charter, since the sponsor is responsible for the overall intent of the project. A team meeting and/or review of the business case may be required to develop input, but the sponsor has final approval. Changes should be managed by the project manager, but a change request is insufficient in this case as the sponsor has final approval.
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Answer explanation
Bottom-up is correct because it is a method of estimating project duration or cost by aggregating the estimates of the lower level components of the WBS and precision level is higher. Analogous is not correct because it is a technique for estimating the duration or cost of an activity or a project using historical data from a similar activity or project. Three-point is not correct because duration estimates based on three points with an assumed distribution provide an expected duration and clarify the range of uncertainty around the expected duration. Reserve analysis is not correct because it covers Contingency and Management reserves. Contingency reserves are associated with the “known-unknowns,” which may be estimated to account for this unknown amount of rework. Management reserves are a specified amount of the project duration withheld for management control purposes and are reserved for unforeseen work that is within scope of the project.
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Answer explanation
The project manager needs to capture any lessons learned from the resource while the information is fresh and to allow for any learned improvements to be implemented earlier. Tasks for the new project are not the current PM's concern. Training the replacement may be needed, but is not the primary issue or the best answer. Selecting a different person to fill the need is neither the PM's choice nor the most important aspect of the situation.
Create a free account and access millions of resources
Similar Resources on Quizizz
15 questions
Project Management

Quiz
•
Professional Development
11 questions
Team Meeting

Quiz
•
Professional Development
15 questions
Diplomado Intec - Ágil

Quiz
•
Professional Development
8 questions
Lesson 5 | Support Project Team Performance

Quiz
•
Professional Development
10 questions
Leadership & Management

Quiz
•
Professional Development
15 questions
Week 1 Review test

Quiz
•
Professional Development
14 questions
Business Sentences - Improvement points

Quiz
•
Professional Development
10 questions
Leadership Bumimulia

Quiz
•
Professional Development
Popular Resources on Quizizz
15 questions
Character Analysis

Quiz
•
4th Grade
17 questions
Chapter 12 - Doing the Right Thing

Quiz
•
9th - 12th Grade
10 questions
American Flag

Quiz
•
1st - 2nd Grade
20 questions
Reading Comprehension

Quiz
•
5th Grade
30 questions
Linear Inequalities

Quiz
•
9th - 12th Grade
20 questions
Types of Credit

Quiz
•
9th - 12th Grade
18 questions
Full S.T.E.A.M. Ahead Summer Academy Pre-Test 24-25

Quiz
•
5th Grade
14 questions
Misplaced and Dangling Modifiers

Quiz
•
6th - 8th Grade