2023S Review Questions 4

Quiz
•
Business
•
Professional Development
•
Hard
Lcit Pmguild
FREE Resource
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Answer explanation
To understand how the project aligns with the organization's strategy, the stakeholder needs to evaluate the goals, objectives, benefits and risk to see how they compare to the organizations goals and risk tolerance. The cost, schedule, risks and WBS provides details on the project activities, but not the detail to compare to the overall strategy. Likewise, the benefits, effort and resources, or schedule, benefits, and WBS would not provide enough detail to compare to the strategy.
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Answer explanation
The question notes the necessary resources are working on another project, indicating that it is a shared resource in either a functional or matrix type organization where the functional manager is the person who is able to reschedule, reassign or replace resources. Negotiate a solution with the functional manager and project sponsor would be the case in this type of organization structure. Outsource the resource necessary to address the risk may be a potential outcome, however not until the discussion is held with the functional manager and project sponsor. Modify the project schedule has no relevance to the question and the issue at hand. Meet with project sponsor to request additional resources and schedule delay, may be a potential outcome, however not until the discussion is held with the functional manager and project sponsor.
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Answer explanation
Scope creep can be avoided or minimized by defining a specific scope baseline and adhering to the agreed upon change control process.
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Answer explanation
As per the new ECO task 1.7: Address and remove impediments, obstacles, and blockers for the team. This also falls into the servant leadership role a PM needs to have in Agile and hybrid environments. As a top priority, the need for the Project Manager is to remove the obstacles and blockers. The other answer choices are incorrect. Documentation is not a priority in Agile hybrid environments, hence adding blockers to the issue log and creating risk management plan can be done as a secondary step and hence is not the correct answer. The scenario described in the question does not indicate that the stakeholders are communicating with the team directly, hence this choice is not the correct answer.
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Answer explanation
Sponsor approval is required for changes to the charter, since the sponsor is responsible for the overall intent of the project. A team meeting and/or review of the business case may be required to develop input, but the sponsor has final approval. Changes should be managed by the project manager, but a change request is insufficient in this case as the sponsor has final approval.
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Answer explanation
Bottom-up is correct because it is a method of estimating project duration or cost by aggregating the estimates of the lower level components of the WBS and precision level is higher. Analogous is not correct because it is a technique for estimating the duration or cost of an activity or a project using historical data from a similar activity or project. Three-point is not correct because duration estimates based on three points with an assumed distribution provide an expected duration and clarify the range of uncertainty around the expected duration. Reserve analysis is not correct because it covers Contingency and Management reserves. Contingency reserves are associated with the “known-unknowns,” which may be estimated to account for this unknown amount of rework. Management reserves are a specified amount of the project duration withheld for management control purposes and are reserved for unforeseen work that is within scope of the project.
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Answer explanation
The project manager needs to capture any lessons learned from the resource while the information is fresh and to allow for any learned improvements to be implemented earlier. Tasks for the new project are not the current PM's concern. Training the replacement may be needed, but is not the primary issue or the best answer. Selecting a different person to fill the need is neither the PM's choice nor the most important aspect of the situation.
Create a free account and access millions of resources
Similar Resources on Wayground
14 questions
Scrum Training - day 1

Quiz
•
Professional Development
7 questions
Group Activity: Sort Employees into D1–D4

Quiz
•
Professional Development
12 questions
Level 3 EAL 002 Unit LO-3 Quiz-1

Quiz
•
Professional Development
10 questions
BEA Oct 30

Quiz
•
Professional Development
9 questions
Impact Project Sprints

Quiz
•
Professional Development
11 questions
Townhall Quiz

Quiz
•
Professional Development
12 questions
Gala Quizz

Quiz
•
Professional Development
10 questions
Introduction to Management

Quiz
•
University - Professi...
Popular Resources on Wayground
18 questions
Writing Launch Day 1

Lesson
•
3rd Grade
11 questions
Hallway & Bathroom Expectations

Quiz
•
6th - 8th Grade
11 questions
Standard Response Protocol

Quiz
•
6th - 8th Grade
40 questions
Algebra Review Topics

Quiz
•
9th - 12th Grade
4 questions
Exit Ticket 7/29

Quiz
•
8th Grade
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
19 questions
Handbook Overview

Lesson
•
9th - 12th Grade
20 questions
Subject-Verb Agreement

Quiz
•
9th Grade