Last lesson quizizz

Last lesson quizizz

Professional Development

13 Qs

quiz-placeholder

Similar activities

Prestressed Concrete HW 1a

Prestressed Concrete HW 1a

Professional Development

11 Qs

Introduction to Project Management

Introduction to Project Management

Professional Development

10 Qs

Unilever Quiz

Unilever Quiz

KG - Professional Development

11 Qs

Bid and Tender Management

Bid and Tender Management

Professional Development

12 Qs

ERP MFG Sales

ERP MFG Sales

Professional Development

15 Qs

Cali Training Day 2

Cali Training Day 2

Professional Development

13 Qs

Sourcing Change and Localization

Sourcing Change and Localization

Professional Development

10 Qs

Chapter 12

Chapter 12

Professional Development

10 Qs

Last lesson quizizz

Last lesson quizizz

Assessment

Quiz

Professional Development

Professional Development

Medium

Created by

Lim Loong Wong

Used 5+ times

FREE Resource

13 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A major difficulty in using EVA is how to estimate the .....

planned cost

total planned budget

duration of the tasks

% completion of the tasks

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In the EVA calculations, which of the following computations must be done first to predict future performance.

CV

SV

CV & SV

CPI & SPI

3.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

EVA is used to monitor project progress and to determine corrective actions. As such, a one-time calculation of all the indices is sufficient.

True

False

4.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

EVA is powerful tool in project management because it measures progress in project's .....

cost

schedule

quality

team work

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In risk management, we focus on risks with .....

highest probability

highest impact

highest severity

highest manpower needs

6.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

The major objective of risk management for adverse events is to .....

maximize the probability

minimize the probability

minimize the impact

maximize the impact

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The phase of project management where we focus on transfer of risk knowledge.

Initiating

Executing

Closing

All phases

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?