
3-3 Administrative Procedures & Protocols
Authored by Centari Rodriguez
Architecture
University
Used 2+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
13 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A contract for the construction of a three-story condominium project has been signed based on completed construction documents, but construction has not yet begun. The owner requests major changes to the plan layout that will increase the project cost.
What document should the architect use to accommodate the request?
Addendum
Change order
Request for information
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A contractor prepares a concrete materials submittal that includes cementitious materials and aggregates, curing materials, floor and slab treatments, reinforcement accessories, an air-entraining admixture, and a floor sealer that is a substitution for the specified sealer. The architect approves the submittal without exception.
During installation of the tile flooring, it is discovered that the specified floor tile adhesive is incompatible with the substituted floor sealer. A compatible adhesive is ordered, which requires extra time to deliver, and the general contractor submits a claim for a time extension and the extra costs.
How should this claim be resolved?
The architect should accept the claim because the submittal was approved.
The general contractor is responsible for extra costs and time delays.
The tile subcontractor must supply a compatible adhesive at their own cost.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During construction, a painting subcontractor informs the architect that they have not been paid on previously approved pay applications and that they are considering leaving the job due to non-payment. The general contractor fails to provide evidence that they have paid the painting subcontractor. The architect believes the general contractor is not financially able to pay their subcontractors.
What should the architect recommend to the owner?
Issue payments for painting subcontractor with joint checks.
Request performance and payment bond from the general contractor.
Deduct the painting costs from the general contractor and pay the subcontractor directly.
4.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
An architect finds items of nonconforming work during a construction site punch walk. Damaged ceiling tiles, malfunctioning light fixtures, and portions of the rubber wall base that have not adhered will all need to be corrected before substantial completion.
What next steps should the architect take to ensure substantial completion of the project? Check the two that apply.
Advise the owner to hire a different contractor to correct the nonconforming work.
Advise the contractor on construction means and methods for fixing the work.
Issue a field observation report listing all the rejected work items immediately after the site visit.
Issue a stop work order on the construction until the nonconforming work is fixed.
Determine the source of the nonconforming work in coordination with the consultant team.
5.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
The 21st and 22nd floors of an existing 25-story office building are being renovated. The primary elevators serving those floors will be replaced with newer, high-speed models.
Which of the following should the architect expect to be part of the elevator submittal review? Check the four that apply.
Shaft and pit dimensions
Cab finish samples
Machine room controller
Operating panels
Warranties and maintenance contracts
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A 15,000-square-foot privately-owned healthcare clinic is under construction and 30% complete. It is experiencing multiple delays and is in danger of missing the scheduled substantial completion date in the contract. The owner-contractor agreement calls for liquidated damages of $1,000 per day.
The contractor has documented the causes of the delays and claims no responsibility for them. The architect and owner agree with the contractor's claim on some of the delays but dispute others. The parties have not been able to negotiate a resolution on the discrepancies. The owner's primary concerns are holding to the substantial completion date in the contract and avoiding legal proceedings.
What should the architect recommend to the owner?
Request a schedule from the contractor to meet the substantial completion date with no additional costs to the owner.
Amend the contract to include a bonus provision to meet the stipulated substantial completion date.
Prepare to seek liquidated damages upon project completion.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Soon before completion of a new shopping center, an owner decides that the building signage is too small and requests the installation of new, larger signage before the shopping center opens. While signage is not part of the contract, the architect and engineer determine the new signage will require additional structural support and foundation reinforcing. They revise the drawings and issue them as part of the architect's supplemental instruction.
The contractor states that the change will have an impact on material and labor costs that will need to be determined by a cost estimator, but a cost estimate cannot be negotiated before the owner's desired opening date.
How should the architect address the owner's request?
Reissue as a change order without the cost of material/labor.
Send the matter to third-party arbitration.
Issue a construction change directive.
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
10 questions
SITE VISIT QUIZ
Quiz
•
University
16 questions
Random Construction Questions
Quiz
•
11th Grade - University
10 questions
Introduction to CAD
Quiz
•
7th Grade - University
16 questions
Ancient Rome Architecture
Quiz
•
University
10 questions
Timber Lecture
Quiz
•
University
10 questions
4) Building Economics and certificates
Quiz
•
University
10 questions
Construction Drawings 15
Quiz
•
9th Grade - University
15 questions
Famous Buildings and their Architects
Quiz
•
8th Grade - Professio...
Popular Resources on Wayground
15 questions
Fractions on a Number Line
Quiz
•
3rd Grade
20 questions
Equivalent Fractions
Quiz
•
3rd Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
54 questions
Analyzing Line Graphs & Tables
Quiz
•
4th Grade
22 questions
fractions
Quiz
•
3rd Grade
20 questions
Main Idea and Details
Quiz
•
5th Grade
20 questions
Context Clues
Quiz
•
6th Grade
15 questions
Equivalent Fractions
Quiz
•
4th Grade
Discover more resources for Architecture
7 questions
How James Brown Invented Funk
Interactive video
•
10th Grade - University
5 questions
Helping Build the Internet: Valerie Thomas | Great Minds
Interactive video
•
11th Grade - University
12 questions
IREAD Week 4 - Review
Quiz
•
3rd Grade - University
23 questions
Subject Verb Agreement
Quiz
•
9th Grade - University
7 questions
Renewable and Nonrenewable Resources
Interactive video
•
4th Grade - University
19 questions
Review2-TEACHER
Quiz
•
University
15 questions
Pre2_STUDENT
Quiz
•
University
20 questions
Ch. 7 Quadrilateral Quiz Review
Quiz
•
KG - University