3-3 Administrative Procedures & Protocols

3-3 Administrative Procedures & Protocols

University

13 Qs

quiz-placeholder

Similar activities

BLDG LAWS PD1096

BLDG LAWS PD1096

University

15 Qs

L: SET 1

L: SET 1

University

10 Qs

Architecture

Architecture

University

10 Qs

Key Players in Construction

Key Players in Construction

University

10 Qs

2-3 Contracts

2-3 Contracts

University

14 Qs

Professional Practice Quiz#3

Professional Practice Quiz#3

University

10 Qs

L: SET 0

L: SET 0

University - Professional Development

10 Qs

PD 1096

PD 1096

University

15 Qs

3-3 Administrative Procedures & Protocols

3-3 Administrative Procedures & Protocols

Assessment

Quiz

Architecture

University

Hard

Created by

Centari Rodriguez

Used 2+ times

FREE Resource

13 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A contract for the construction of a three-story condominium project has been signed based on completed construction documents, but construction has not yet begun. The owner requests major changes to the plan layout that will increase the project cost.

What document should the architect use to accommodate the request?

Addendum

Change order

Request for information

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A contractor prepares a concrete materials submittal that includes cementitious materials and aggregates, curing materials, floor and slab treatments, reinforcement accessories, an air-entraining admixture, and a floor sealer that is a substitution for the specified sealer. The architect approves the submittal without exception.

During installation of the tile flooring, it is discovered that the specified floor tile adhesive is incompatible with the substituted floor sealer. A compatible adhesive is ordered, which requires extra time to deliver, and the general contractor submits a claim for a time extension and the extra costs. 

How should this claim be resolved?

The architect should accept the claim because the submittal was approved.


The general contractor is responsible for extra costs and time delays.

The tile subcontractor must supply a compatible adhesive at their own cost.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During construction, a painting subcontractor informs the architect that they have not been paid on previously approved pay applications and that they are considering leaving the job due to non-payment. The general contractor fails to provide evidence that they have paid the painting subcontractor. The architect believes the general contractor is not financially able to pay their subcontractors.

What should the architect recommend to the owner?


Issue payments for painting subcontractor with joint checks.


Request performance and payment bond from the general contractor.

Deduct the painting costs from the general contractor and pay the subcontractor directly.

4.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

An architect finds items of nonconforming work during a construction site punch walk. Damaged ceiling tiles, malfunctioning light fixtures, and portions of the rubber wall base that have not adhered will all need to be corrected before substantial completion.

What next steps should the architect take to ensure substantial completion of the project? Check the two that apply.

Advise the owner to hire a different contractor to correct the nonconforming work.

Advise the contractor on construction means and methods for fixing the work.

Issue a field observation report listing all the rejected work items immediately after the site visit.

Issue a stop work order on the construction until the nonconforming work is fixed.

Determine the source of the nonconforming work in coordination with the consultant team.

5.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

The 21st and 22nd floors of an existing 25-story office building are being renovated. The primary elevators serving those floors will be replaced with newer, high-speed models.

Which of the following should the architect expect to be part of the elevator submittal review? Check the four that apply. 

Shaft and pit dimensions


Cab finish samples 

Machine room controller

Operating panels

Warranties and maintenance contracts

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A 15,000-square-foot privately-owned healthcare clinic is under construction and 30% complete. It is experiencing multiple delays and is in danger of missing the scheduled substantial completion date in the contract. The owner-contractor agreement calls for liquidated damages of $1,000 per day.

The contractor has documented the causes of the delays and claims no responsibility for them. The architect and owner agree with the contractor's claim on some of the delays but dispute others. The parties have not been able to negotiate a resolution on the discrepancies. The owner's primary concerns are holding to the substantial completion date in the contract and avoiding legal proceedings.

What should the architect recommend to the owner?

Request a schedule from the contractor to meet the substantial completion date with no additional costs to the owner. 

Amend the contract to include a bonus provision to meet the stipulated substantial completion date.


Prepare to seek liquidated damages upon project completion.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Soon before completion of a new shopping center, an owner decides that the building signage is too small and requests the installation of new, larger signage before the shopping center opens. While signage is not part of the contract, the architect and engineer determine the new signage will require additional structural support and foundation reinforcing. They revise the drawings and issue them as part of the architect's supplemental instruction. 

The contractor states that the change will have an impact on material and labor costs that will need to be determined by a cost estimator, but a cost estimate cannot be negotiated before the owner's desired opening date.

How should the architect address the owner's request?

Reissue as a change order without the cost of material/labor.

Send the matter to third-party arbitration.

Issue a construction change directive.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?