CBAP - RLCM

CBAP - RLCM

Professional Development

9 Qs

quiz-placeholder

Similar activities

RCTCM Staff Training Assessment

RCTCM Staff Training Assessment

Professional Development

10 Qs

Define Phase

Define Phase

Professional Development

5 Qs

Project Management (Week 3)

Project Management (Week 3)

Professional Development

5 Qs

Activity Quiz

Activity Quiz

University - Professional Development

8 Qs

HSSE Mgt Quiz 1

HSSE Mgt Quiz 1

Professional Development

10 Qs

1. Day 1_ITBA 10 Soal

1. Day 1_ITBA 10 Soal

KG - Professional Development

10 Qs

RLCM

RLCM

Professional Development

10 Qs

PLAL Agile Onboarding

PLAL Agile Onboarding

Professional Development

10 Qs

CBAP - RLCM

CBAP - RLCM

Assessment

Quiz

Education

Professional Development

Hard

Created by

Rachana Patil

Used 16+ times

FREE Resource

9 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

You are a business analyst working on a regulatory project. The lead

business analyst asks you to prioritize requirements in order to meet the

regulatory demands imposed on the organization over other stakeholder

interests. What factor is influencing this prioritization?

Penalty

Risk

Governance

Time Sensitivity

Answer explanation

Penalty is a prioritization factor that speaks to the consequences from not implementing a given requirement (e.g., regulatory fines). BABOK 5.3.4.1

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

You are working on a team that is adding a new line of insurance to your company's claims system. Conflicts have arisen among many of the stakeholders as a result of different interpretations of requirements for the new line as well as conflicting values placed on their value. Which stakeholder would you recommend facilitating communication between stakeholders to resolve the areas of conflict so that each group has an improved appreciation for the needs of the others?

Human resources

Business analyst

Project manager

Sponsor

Answer explanation

Consensus among stakeholders is usually sought prior to requesting approval of requirements. During this process, stakeholder groups frequently have varying points of view. The business analyst facilitates communication between stakeholders. BABOK 5.5.4.2

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A guideline provides instructions or descriptions on why or how to undertake a task, while a tool is something used to

undertake a task. Which of the following is NOT listed as a "guideline and tool" in requirement life cycle management?

Business analysis

approach

Domain Knowledge

Requirements

architecture

Information

management

approach

Answer explanation

This is not one of the guidelines or tools listed for RLCM, making it the correct answer. BABOK 5.0

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Beau is a BA working on a telecommunications project. The business architect gives him a

reference model called "eTOM", commonly used in the communications sector. What value might this have for Beau?

It will have little

value to Beau as he

is focused on

Information

Technology.

The model will

provide Beau with

information

regarding how

work is currently

performed and the

information

required to

complete work.

The model will

provide Beau with

understanding of

how the strategic

objectives of the

organization are

aligned with

tactical demands

and activities in

the current state

of the enterprise.

The model will

provide Beau with

an understanding

of how the

organization

currently delivers

value to

customers.

Answer explanation

A reference model called "eTOM" is utilized within communication industries to model business architecture. BABOK Table 11.4.1

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Hrishi is the business analyst for an organization and she's coaching Shivali, a new business analyst, on the importance of

identifying and recording key dependencies between requirements. Which one of the following is the primary reason why key

dependencies should be identified and recorded?

To help achieve

efficiency by

implementing

related

requirements at

the same time.

To identify the

relative risk of

each requirement

To determine who

owns the

requirement in the

project life cycle.

To identify the

benefit of each

requirement

Answer explanation

Identifying and documenting dependencies assists the business analyst in sequencing

project work activities to design and deploy the capabilities found in the requirements. It

also assists the business analyst in correctly allocating requirements to solution components. BABOK 5.3.4 and 7.6.4.4

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following considerations is NOT addressed when assessing the impact of a

proposed change?

The business

analyst evaluates

cost of the change,

the cost of any

associated work,

and opportunity

costs.

The business analyst

evaluates the

impact of the

change on

customers and

business processes

The business

analyst evaluates

the impact of any

change to the

dependencies

between

requirements

The business analyst

evaluates the

benefit that will be

gained by accepting

the change.

Answer explanation

This is not a listed consideration to assessing a proposed change. Although this may be part of the impact analysis, the BABOK does not explicitly state that the analysis of dependencies has to occur when assessing a proposed change. "When a requirement

changes, its relationships to other requirements or solution components can

be reviewed." Watch for fine points like these to eliminate wrong answers. BABOK 5.4.4.2 first paragraph

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which statement best describes why the stakeholder list is important to prioritizing requirements?

It provides the

organizational structure

that will be impacted by

the solution

It ensures all stakeholders

have been involved in the

requirements

management plan, which

provides the process for

prioritization of

requirements

It indicates levels of

power to determine

which stakeholders are

needed for

prioritization

It helps the project

manager create the

meeting invitation for the

requirements

prioritization meeting

Answer explanation

The list of requirements approval stakeholders verifies that the prioritized

requirements will deliver value; facilitates

negotiations to have the prioritization changed based on relative value;

provides input relating to technical dependencies; verifies that the prioritization

is consistent with legal; and more. BABOK 5.3.7

8.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

All of the following stakeholders participate in the prioritization of requirements except for which one?

Implementation subject matter expert

Project team

Project Manager

Sponsor

Answer explanation

These are not the listed stakeholders.BABOK v3: 5.3 - Prioritize requirements

9.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

FinTech Corp. has asked the BA to plan the GRC system such that it can handle an increased number of users anywhere between 1000 to 10000 in the next 5 years. The REQ2000 is missing which of the following characteristics?

Specific

  1. Consistent

  1. Concise

  1. Feasible

Answer explanation

REQ2000 does not clearly say how many number of users and hence is not specific.