1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which process ensures that project performance is in line with the project management plan and that changes are properly controlled?
Develop Project Charter
Develop Project Management Plan
Direct and Manage Project Work
Monitor and Control Project Work
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which process involves obtaining formal acceptance of the project deliverables from the customer or relevant stakeholders?
Perform Integrated Change Control
Close Project or Phase
Validate Scope
Monitor and Control Project Work
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The main goal of the Integration Management knowledge area is to:
Define the scope of the project
Develop the project schedule
Coordinate all project activities and ensure they work together
Perform risk analysis for the project
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The process of finalizing all activities across all process groups to formally close a project or phase is:
Perform Integrated Change Control
Close Project or Phase
Direct and Manage Project Work
Monitor and Control Project Work
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the primary purpose of a Change Control Board (CCB) in project management?
To create the project management plan
To monitor project performance
To review and approve changes to the project
To manage project risks
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A Change Control Board (CCB) is particularly important in projects with:
No changes or uncertainties
A rigid and inflexible project management approach
Multiple stakeholders and potential changes
No need for project documentation
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the main purpose of a Lessons Learned Register in project management?
To track project expenditures
To document project risks
To capture and document valuable insights and experiences from the project
To manage project schedules
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
11 questions
PBCC Workshop: Pre-Knowledge Assessment
Quiz
•
Professional Development
11 questions
EVALUACIÓN HISTORIA DE LAS ARMAS
Quiz
•
Professional Development
10 questions
Planificación Educativa
Quiz
•
Professional Development
10 questions
Quiz sobre Salud y Seguridad en el Trabajo
Quiz
•
Professional Development
10 questions
Ice-Breaker Quiz Term 3!
Quiz
•
Professional Development
10 questions
Principles of Language Learning
Quiz
•
Professional Development
10 questions
NASOT
Quiz
•
Professional Development
10 questions
Soal Bahasa Inggris dasar untuk guru SDIT Ahmad Yani Brebes
Quiz
•
Professional Development
Popular Resources on Wayground
15 questions
Fractions on a Number Line
Quiz
•
3rd Grade
20 questions
Equivalent Fractions
Quiz
•
3rd Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
22 questions
fractions
Quiz
•
3rd Grade
20 questions
Main Idea and Details
Quiz
•
5th Grade
20 questions
Context Clues
Quiz
•
6th Grade
15 questions
Equivalent Fractions
Quiz
•
4th Grade
20 questions
Figurative Language Review
Quiz
•
6th Grade