Project Scope Management Knowledge area

Authored by Mariam Nazaryan

Professional Development

Professional Development

Project Scope Management Knowledge area
AI

AI Actions

Add similar questions

Adjust reading levels

Convert to real-world scenario

Translate activity

More...

    Content View

    Student View

11 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which process involves defining and documenting the project's features and functions, as well as the constraints and assumptions?

Collect Requirements

Validate Scope

Define Scope

Control Scope

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During which process is the Work Breakdown Structure (WBS) created?

Define Scope

Plan Scope Management.

Create WBS

Verify Scope

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A change request has been submitted that would significantly impact the project scope. What is the FIRST step you should take?

Implement the change to expedite progress.

Review the change request with the project team

Reject the change request to maintain project stability.

Analyze the potential impact of the change on the project.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does the Control Scope process primarily focus on?

Determining the root causes of scope changes.

Preventing any scope changes from occurring.

Monitoring project performance against the scope baseline.

Finalizing and closing out the project scope.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In which process is the Scope Baseline established?

Define Scope.

Plan Scope Management.

Create WBS.

Control Scope.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During the Verify Scope process, what is the main focus?

Ensuring that all requirements have been met.

Identifying changes to the project scope.

Managing stakeholder expectations.

Tracking project progress.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The project sponsor has requested a change to the project scope that would add significant new features. What should the project manager do first?

Implement the change immediately to satisfy the sponsor.

Analyze the change's impact on the project's cost, schedule, and other constraints.

Inform the team about the change without assessing its feasibility.

Request the sponsor to reconsider the change.

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?

Discover more resources for Professional Development