Project Schedule Management Knowledge area

Project Schedule Management Knowledge area

Professional Development

10 Qs

quiz-placeholder

Similar activities

Duration Estimate In Work Program

Duration Estimate In Work Program

Professional Development

10 Qs

Planning and Scheduling Professional Practice Questions

Planning and Scheduling Professional Practice Questions

Professional Development

9 Qs

Basics of Project management

Basics of Project management

Professional Development

11 Qs

Project Integration Management

Project Integration Management

Professional Development

15 Qs

Project Management Fundamentals - Module 5

Project Management Fundamentals - Module 5

Professional Development

10 Qs

Tech Mastery Day 6

Tech Mastery Day 6

Professional Development

15 Qs

November W-2 III

November W-2 III

Professional Development

15 Qs

Schedule Management Processes - Assignment

Schedule Management Processes - Assignment

Professional Development

6 Qs

Project Schedule Management Knowledge area

Project Schedule Management Knowledge area

Assessment

Quiz

Professional Development

Professional Development

Hard

Created by

Mariam Nazaryan

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the primary goal of the Develop Schedule process in the Schedule Management knowledge area?

To create a detailed task list.

To determine project resource requirements.

To estimate project costs.

To establish the project schedule baseline.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During which process is the critical path determined?

Plan Schedule Management.

Estimate Activity Durations

Develop Schedule.

Control Schedule.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the primary purpose of the Control Schedule process?

To adjust project scope.

To monitor project risks.

To track project performance against the schedule baseline.

To create a detailed task list.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During the Control Schedule process, what does "rebaseline" refer to?

Changing the project scope

Updating the project's risk register.

Creating a new project schedule baseline.

Adding new tasks to the project.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which process involves decomposing project work into smaller, manageable activities to facilitate schedule development?

Plan Schedule Management.

Define Activities.

Estimate Activity Resources.

Develop Schedule.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The project manager is working on a construction project with a fixed completion date. Due to unexpected delays, the project is at risk of not meeting the deadline. What should the project manager do first?

Adjust the project scope to align with the new schedule.

Communicate the issue to stakeholders and assess the impact.

Delegate the issue to the team to find a solution.

Implement additional resources to accelerate tasks.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During the Control Schedule process, the project manager identifies that the project is falling behind the schedule baseline. What corrective action should the project manager take?

Adjust the project scope to accommodate the delays.

Rebaseline the schedule to reflect the delays.

Implement corrective measures to get the project back on track.

Continue as planned, as minor schedule deviations are acceptable.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?