1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Halfway into a software development project, your most experienced programmer resigns leaving only two programmers.The previously planned response to this risk is to acquire a programmer from another project manager, with whom you are not well acquainted. What is the best way for you to handle this situation?
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
An agile team is developing a product for a customer. In the last few iterations, the team members spent extra hourscreating product documentation and reviewing the contracts with the customer. How would the team's time been better spent?
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
You are preparing for an upcoming software development project. The project will be initiated and planned using apredictive approach, while the development team will use Kanban. A budget has been established for training, and you need to determine how to allocate those funds. What is your best course of action?
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A project manager is introducing agile values to a newly formed team. The team is assigned to develop a new softwareapplication using the eXtreme Programming (XP) method. The project manager explains that agile approaches are value-driven in two ways: one way is focusing on features that provide the highest value to the customer. Which of the following did the project manager most likely mention as another way of agile approaches, unique to XP, tobe value-driven?
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
The members of an agile team have been very productive for the last four sprints and performed as a well-organized unit.However, the current sprint is much more complex with many technical difficulties. Two team members have spent daysarguing over the best technical approach to develop the product, while the rest of the team were quiet and disinterested. Where is the team on Tuckman's ladder during the current sprint?
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
An agile team has been working overtime for the last few iterations. The project manager has decided that from now on theteam should maintain a 40-hour work week. What is the most likely reason behind the project manager's decision?
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Four developers have been acquired with a time and materials contract on a software development project. Duringproject execution, the project manager notices that the developers work fewer hours than anticipated, resulting in theproject to fall behind schedule. The project manager contracts two more developers, who help bring the project back ontrack. What should the project manager do after adding the contractors to the team?
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Microsoft
or continue with
%20(1).png)
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?