All-In-One Project+ PK0-005 Exam Guide - Chapter 09

Quiz
•
Professional Development
•
Professional Development
•
Hard

Patrick Pepin
FREE Resource
15 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
You are the project manager of the NYQ Project for your organization.
Your project is slipping on some tasks and you would like to implement duration compression for this project.
Which one of the following is a duration compression technique that generally does not increase risks within the project?
Crashing
Fast tracking
Resource leveling
Lead time for all fixed-duration activities
Answer explanation
Crashing generally does not add risks to the project, but it does add costs because of the added labor.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What should be the goal of the individuals on the project team?
To make the company more profitable
To help each team member finish their tasks
To focus on completing their own tasks
To finish their work as quickly as possible
Answer explanation
The goal of project team members should be to focus on completing their own tasks. If each team member would focus on completing the assignments as planned, the project would flow smoothly.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Why should a project manager host a regularly scheduled team meeting?
A meeting allows team members to report on their activities.
A meeting allows the project manager to make changes to the project scope.
A meeting allows team members to air grievances about other team members.
A meeting allows the stakeholder to identify requirements.
Answer explanation
Regular team meetings accomplish many different tasks including allowing team members to report on their activities and allowing the team to solve project problems as a group.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What concept is defined in the law of diminishing returns?
Work expands to fill the amount of time allotted to it
Padding the time surrounding activities causes project risks.
Adding labor increases project costs.
You cannot continually add labor to reduce project duration.
Answer explanation
The law of diminishing returns addresses the concept of adding labor to reduce the duration of activity.
While you may be able to add labor to decrease the duration of a task, you cannot continually add labor to reduce the duration of the task.
In addition, added labor may become counterproductive for the project.
Finally, the cost of the labor added may not be worth the yield (the value) of the work the added labor is able to perform.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is a work authorization system?
A method to approve work that's been completed
A method for the project stakeholders to approve the project work
A method to allow successor work to begin based on the completion of predecessor work
A method to allow the project manager to track uncompleted milestones
Answer explanation
A work authorization system is a formal process where project team members report the completion of their tasks so that downstream activities may begin.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Why should a project manager allow team members to report on completed milestones in a team meeting?
To create team development through project work
To create a sense of pride in the work accomplished
To create internal competition on the project
To create peer pressure to outdo the other team members
Answer explanation
By requiring team members to report verbally on the status of their assignments, they are held accountable for their activities.
In addition, this practice creates a sense of pride for the team members who have accomplished major milestones in the project.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Why should you review the upcoming assignments in a project team meeting?
To remind the team members of the work they must complete
To remind the team that you are in charge of the project
To confirm that team members know their duties for last week
To confirm that the project is moving and on track
Answer explanation
By reviewing the assignments with the project team, you are ensuring that the project is moving and on track.
At the same time, you are confirming that the team members know their duties for the week and reminding them what their assignments are - but overall, the purpose is to keep the project moving.
Create a free account and access millions of resources
Similar Resources on Wayground
10 questions
Resource Mgmt Pre-test

Quiz
•
Professional Development
20 questions
Quiziz Week 3 Day 2

Quiz
•
Professional Development
10 questions
PMP - PROJECT INTEGRATION

Quiz
•
Professional Development
20 questions
Project management Cycle

Quiz
•
Professional Development
10 questions
Project Closure

Quiz
•
Professional Development
13 questions
PMP Exam Preparation Mocktest With Formula

Quiz
•
Professional Development
10 questions
Project Management Fundamentals - Module 5

Quiz
•
Professional Development
10 questions
Project Management

Quiz
•
Professional Development
Popular Resources on Wayground
50 questions
Trivia 7/25

Quiz
•
12th Grade
11 questions
Standard Response Protocol

Quiz
•
6th - 8th Grade
11 questions
Negative Exponents

Quiz
•
7th - 8th Grade
12 questions
Exponent Expressions

Quiz
•
6th Grade
4 questions
Exit Ticket 7/29

Quiz
•
8th Grade
20 questions
Subject-Verb Agreement

Quiz
•
9th Grade
20 questions
One Step Equations All Operations

Quiz
•
6th - 7th Grade
18 questions
"A Quilt of a Country"

Quiz
•
9th Grade