All-In-One Project+ PK0-005 Exam Guide - Chapter 09

All-In-One Project+ PK0-005 Exam Guide - Chapter 09

Professional Development

15 Qs

quiz-placeholder

Similar activities

Proj Integration Management

Proj Integration Management

Professional Development

15 Qs

Recruitment-Oriented Case Studies Quiz

Recruitment-Oriented Case Studies Quiz

Professional Development

20 Qs

Chapter 12

Chapter 12

University - Professional Development

10 Qs

digital product/project management

digital product/project management

Professional Development

20 Qs

Scrum Stars

Scrum Stars

Professional Development

10 Qs

UPIP PMP-Scheduling-Cost-quality

UPIP PMP-Scheduling-Cost-quality

Professional Development

12 Qs

PMP Assessment

PMP Assessment

Professional Development

20 Qs

Atoha PMP lesson 14

Atoha PMP lesson 14

Professional Development

10 Qs

All-In-One Project+ PK0-005 Exam Guide - Chapter 09

All-In-One Project+ PK0-005 Exam Guide - Chapter 09

Assessment

Quiz

Professional Development

Professional Development

Hard

Created by

Patrick Pepin

FREE Resource

15 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

You are the project manager of the NYQ Project for your organization.

Your project is slipping on some tasks and you would like to implement duration compression for this project.

Which one of the following is a duration compression technique that generally does not increase risks within the project?

Crashing

Fast tracking

Resource leveling

  1. Lead time for all fixed-duration activities

Answer explanation

Crashing generally does not add risks to the project, but it does add costs because of the added labor.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What should be the goal of the individuals on the project team?

To make the company more profitable

  1. To help each team member finish their tasks

To focus on completing their own tasks

To finish their work as quickly as possible

Answer explanation

The goal of project team members should be to focus on completing their own tasks. If each team member would focus on completing the assignments as planned, the project would flow smoothly.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Why should a project manager host a regularly scheduled team meeting?

A meeting allows team members to report on their activities.

  1. A meeting allows the project manager to make changes to the project scope.

  1. A meeting allows team members to air grievances about other team members.

A meeting allows the stakeholder to identify requirements.

Answer explanation

Regular team meetings accomplish many different tasks including allowing team members to report on their activities and allowing the team to solve project problems as a group.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What concept is defined in the law of diminishing returns?

Work expands to fill the amount of time allotted to it

  1. Padding the time surrounding activities causes project risks.

Adding labor increases project costs.

You cannot continually add labor to reduce project duration.

Answer explanation

  1. The law of diminishing returns addresses the concept of adding labor to reduce the duration of activity.

  2. While you may be able to add labor to decrease the duration of a task, you cannot continually add labor to reduce the duration of the task.

  3. In addition, added labor may become counterproductive for the project.


  4. Finally, the cost of the labor added may not be worth the yield (the value) of the work the added labor is able to perform.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is a work authorization system?

  1. A method to approve work that's been completed

  1. A method for the project stakeholders to approve the project work

A method to allow successor work to begin based on the completion of predecessor work

A method to allow the project manager to track uncompleted milestones

Answer explanation

A work authorization system is a formal process where project team members report the completion of their tasks so that downstream activities may begin.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Why should a project manager allow team members to report on completed milestones in a team meeting?

  1. To create team development through project work

To create a sense of pride in the work accomplished

To create internal competition on the project

  1. To create peer pressure to outdo the other team members

Answer explanation

  1. By requiring team members to report verbally on the status of their assignments, they are held accountable for their activities.

  2. In addition, this practice creates a sense of pride for the team members who have accomplished major milestones in the project.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Why should you review the upcoming assignments in a project team meeting?

  1. To remind the team members of the work they must complete

  1. To remind the team that you are in charge of the project

  1. To confirm that team members know their duties for last week

To confirm that the project is moving and on track

Answer explanation

  1. By reviewing the assignments with the project team, you are ensuring that the project is moving and on track.

  2. At the same time, you are confirming that the team members know their duties for the week and reminding them what their assignments are - but overall, the purpose is to keep the project moving.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?