A project manager leaves the company and is replaced. The new project manager is excited to start guiding the team toward project success.
What should the new project manager do first?
PMP Team Quiz

Quiz
•
Professional Development
•
Professional Development
•
Hard
Jorge Estrada
Used 8+ times
FREE Resource
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Try the new Pizza Burger at the Cafeteria before it’s gone!
Modify the project schedule, adding a new activity related to the knowledge transfer process.
Revisit the project budget and schedule to determine if extra time is required.
Review the project charter to identify goals and deliverables.
Answer explanation
The first thing a new project manager should do is to understand the project charter which outlines the project's goals and deliverables. This will help guide them in further decision making and planning. While revisiting the budget, schedule, and transferring knowledge are important, they come after understanding the basic framework of the project.
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Which organizational structure is a combination of all the types of organizations?
Matrix
Hybrid
Depends on the eye of the beholder
Offices with great cafeterias
Answer explanation
The correct answer to the question is 'Matrix'. A matrix organization structure combines the characteristics of various types of organizations. It typically involves a combination of functional and project-oriented structures, allowing for the benefits of both.
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A Project Manager receives the following for a new project:
-assumptions
-restrictions
-preliminary scope
After receiving this information, what should the Project Manager do first?
Take 15 minutes break so he doesn’t get stressed by upper Management.
Review and understand the business case and project goals.
Take a 30 minute nap, no more.
Build the project schedule and determine the critical path.
Answer explanation
The Project Manager should first review and understand the business case and project goals. This is the correct option because it allows them to understand the project's context and its objectives, which are essential for making decisions about the assumptions, restrictions, and preliminary scope.
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A week prior to the project kick-off call, a Project Manager meets with a key project resource to gain a deeper understanding of how complex the project deliverables are.
The resource expresses concern and worry regarding the deliverables.
What should the Project Manager do to ensure that the deliverables are realistic?
Pick another Project and ignore that one for a little while.
Perform a feasibility study, and then assess the results.
Probably someone will cancel it. Request PTO ASAP.
Identify threats and preventive actions by conducting a risk assessment.
5.
MULTIPLE CHOICE QUESTION
3 mins • 2 pts
Senior management asked you to consider the types of organizational structures and working styles that might be followed at your development company that builds homes for low-income families, and the possible impact on the project you will be managing. Your organization has departments for donations, construction, marketing, volunteers, and finance. But before you start working on it, you need to verify your knowledge on the organizational structures and functions.
In addition to the departments listed in the scenario, your company also has a manager of project management to oversee all of the ongoing projects. As one of the project managers, you report directly to the project management department but share staff with other departments. What type of organizational structure does this describe?
A difficult one.
Projectized
Matrix
Functional
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A new product development project is to be initiated in a difficult business context. Competition is driving prices down, and supply costs are rising.
Why would an agile incremental project approach be the safest choice in this context?
It reduces the team size and eliminates communication bottlenecks.
It accelerates delivery of business value and minimizes risk of irrelevancy.
It provides stringent methods to reduce cost of quality and conformity.
It ensures that the project can be cancelled at any time without loss.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project team is worried about product packaging and presentation. They receive a lot of negative feedback about this during iteration demos.
How can the team improve their chances of customer acceptance?
Use Christmas wrapping.
Revise the definition of done (DoD) with the customer.
Look through the customer’s social media accounts and perform a qualitative analysis of customer attitudes towards packaging.
Put the Customer on Time Out.
Create a free account and access millions of resources
Similar Resources on Quizizz
7 questions
Integration Process - Assignment

Quiz
•
Professional Development
10 questions
Communication 10 soal (Chapter 10)

Quiz
•
Professional Development
10 questions
Procurement 10 soal (Chapter 12)

Quiz
•
Professional Development
12 questions
Project Management Master Class 2

Quiz
•
Professional Development
12 questions
Waterfall Mindset1(AKF)

Quiz
•
Professional Development
10 questions
Resource Mgmt Pre-test

Quiz
•
Professional Development
10 questions
PMP - PROJECT INTEGRATION

Quiz
•
Professional Development
10 questions
PMP - Roles & Organizations

Quiz
•
Professional Development
Popular Resources on Quizizz
15 questions
Character Analysis

Quiz
•
4th Grade
17 questions
Chapter 12 - Doing the Right Thing

Quiz
•
9th - 12th Grade
10 questions
American Flag

Quiz
•
1st - 2nd Grade
20 questions
Reading Comprehension

Quiz
•
5th Grade
30 questions
Linear Inequalities

Quiz
•
9th - 12th Grade
20 questions
Types of Credit

Quiz
•
9th - 12th Grade
18 questions
Full S.T.E.A.M. Ahead Summer Academy Pre-Test 24-25

Quiz
•
5th Grade
14 questions
Misplaced and Dangling Modifiers

Quiz
•
6th - 8th Grade