SPM Midterm (FIT HANU)
Quiz
•
Education
•
University
•
Practice Problem
•
Medium
Shiroi Kitsunee
Used 54+ times
FREE Resource
Enhance your content in a minute
131 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Approximately what percentage of the world’s gross product is spent on projects?
A. 10 percent
B. 25 percent
C. 50 percent
D. 75 percent
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is not a potential advantage of using good project management?
A. Shorter development times
B. Higher worker morale
C. Lower cost of capital
D. Higher profit margins
Answer explanation
cost of capital: chi phí đầu tư bỏ ra -> Chi phí xây dựng phần mềm chỉ tăng lên chứ không giảm đi
Profit margins: lợi nhuận thu được.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A ________ is a temporary endeavor undertaken to create a unique product, service, or result.
A. program
B. process
C. project
D. portfolio
Answer explanation
Portfolio(n): những chương trình mang tính chiến lược, không liên quan tới nhau.
Process(n): các tiến trình làm bên trong project.
Program(n): một chương trình, bao gồm nhiều project có liên quan tới nhau.
Project(n): một dự án độc lập, bao gồm nhiều process.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is not an attribute of a project?
A. projects are unique
B. projects are developed using progressive elaboration
C. projects have a primary customer or sponsor
D. projects involve little uncertainty
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is not part of the triple constraint of project management?
A. meeting scope goals
B. meeting time goals
C. meeting communications goals
D. meeting cost goals
Answer explanation
meeting communications goals chỉ là phần bổ trợ trong dự án
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
______ is the application of knowledge, skills, tools, and techniques to project activities to meet project requirements.
A. Project management
B. Program management
C. Project portfolio management
D. Requirements management
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Project portfolio management addresses ______ goals of an organization, while project management addresses _______ goals.
A. strategic, tactical
B. tactical, strategic
C. internal, external
D. external, internal
Create a free account and access millions of resources
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
Popular Resources on Wayground
5 questions
This is not a...winter edition (Drawing game)
Quiz
•
1st - 5th Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
10 questions
Identify Iconic Christmas Movie Scenes
Interactive video
•
6th - 10th Grade
20 questions
Christmas Trivia
Quiz
•
6th - 8th Grade
18 questions
Kids Christmas Trivia
Quiz
•
KG - 5th Grade
11 questions
How well do you know your Christmas Characters?
Lesson
•
3rd Grade
14 questions
Christmas Trivia
Quiz
•
5th Grade
20 questions
How the Grinch Stole Christmas
Quiz
•
5th Grade
Discover more resources for Education
26 questions
Christmas Movie Trivia
Lesson
•
8th Grade - Professio...
20 questions
christmas songs
Quiz
•
KG - University
20 questions
Holiday Trivia
Quiz
•
9th Grade - University
15 questions
Holiday Movies
Quiz
•
University
14 questions
Christmas Trivia
Quiz
•
3rd Grade - University
20 questions
Christmas Trivia
Quiz
•
University
8 questions
5th, Unit 4, Lesson 8
Lesson
•
KG - Professional Dev...
20 questions
Disney Trivia
Quiz
•
University