SPM Midterm (FIT HANU)

SPM Midterm (FIT HANU)

University

131 Qs

quiz-placeholder

Similar activities

การจัดการเรียนรู้ (สอบกลางภาค)

การจัดการเรียนรู้ (สอบกลางภาค)

University

130 Qs

ATLETIK

ATLETIK

University

130 Qs

ATBM plus

ATBM plus

University

131 Qs

Вопросы по игровому дизайну

Вопросы по игровому дизайну

12th Grade - University

126 Qs

fisika bab vektor

fisika bab vektor

11th Grade - University

131 Qs

C1-C4 KTCTMacLenin

C1-C4 KTCTMacLenin

University

135 Qs

Prawo gospodarcze

Prawo gospodarcze

University

128 Qs

Trắc nghiệm Tâm lý học

Trắc nghiệm Tâm lý học

University

131 Qs

SPM Midterm (FIT HANU)

SPM Midterm (FIT HANU)

Assessment

Quiz

Education

University

Practice Problem

Medium

Created by

Shiroi Kitsunee

Used 54+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

131 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Approximately what percentage of the world’s gross product is spent on projects?

A. 10 percent

B. 25 percent

C. 50 percent

D. 75 percent

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is not a potential advantage of using good project management?

A. Shorter development times

B. Higher worker morale

C. Lower cost of capital

D. Higher profit margins

Answer explanation

cost of capital: chi phí đầu tư bỏ ra -> Chi phí xây dựng phần mềm chỉ tăng lên chứ không giảm đi

Profit margins: lợi nhuận thu được.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A ________ is a temporary endeavor undertaken to create a unique product, service, or result.

A. program

B. process

C. project

D. portfolio

Answer explanation

Portfolio(n): những chương trình mang tính chiến lược, không liên quan tới nhau.

Process(n): các tiến trình làm bên trong project.

Program(n): một chương trình, bao gồm nhiều project có liên quan tới nhau.

Project(n): một dự án độc lập, bao gồm nhiều process.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is not an attribute of a project?

A. projects are unique

B. projects are developed using progressive elaboration

C. projects have a primary customer or sponsor

D. projects involve little uncertainty

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is not part of the triple constraint of project management?

A. meeting scope goals

B. meeting time goals

C. meeting communications goals

D. meeting cost goals

Answer explanation

meeting communications goals chỉ là phần bổ trợ trong dự án

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

______ is the application of knowledge, skills, tools, and techniques to project activities to meet project requirements.

A. Project management

B. Program management

C. Project portfolio management

D. Requirements management

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Project portfolio management addresses ______ goals of an organization, while project management addresses _______ goals.

A. strategic, tactical

B. tactical, strategic

C. internal, external

D. external, internal

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?