1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The full form of PERT is

Program Evaluation and Rate Technology

Program Evaluation and Robot Technique

Program Evaluation and Review Technique

Program Evaluation and Robot Technology

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The full form of CPM is

Critical Path Method

Critical Plan Management

Control Path Method

Control Path Management

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A PERT network is activity-oriented while a CPM network is event-oriented.

True

False

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The difference between the maximum time available and the actual time needed to perform an activity is known as

Free float

Total float

Independent float

Half float

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A set of values of decision variables that satisfies the linear constraints and non-negativity conditions of an L.P.P. is called its:

Unbounded solution

Optimum solution

Feasible solution

None of these

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is a type of Linear programming problem?

Manufacturing problem

Diet problem

Transportation problems

All of the above

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The objective function of a linear programming problem is:

a constraint

function to be optimised

None of these

A relation between the variables

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?