Sanitation Systems phase 2 1.5

Authored by Daniel Edwards

Architecture

Professional Development

Used 5+ times

Sanitation Systems phase 2 1.5
AI

AI Actions

Add similar questions

Adjust reading levels

Convert to real-world scenario

Translate activity

More...

    Content View

    Student View

13 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Why is it important to position waste pipe systems and soil pipe systems with care inside buildings?

To improve the aesthetics of the building

To save money on materials

To prevent damage to the building fabric

To make it easier to install the pipes

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What happens if notching of joists is done when the pipe is greater in diameter than 1/8 of the joist depth?

The joist strength will be severely compromised

The joist will become stronger

The pipe will be easier to install

The pipe will become unstable

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Can waste pipe systems and soil pipe systems be positioned across the joist run?

Yes, it is the recommended positioning

No, it is not recommended

It doesn't matter

Only if the pipes are small in diameter

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the maximum diameter of the pipe that can be notched into a joist?

1/8 of the joist depth

1/2 of the joist depth

The full joist depth

1/4 of the joist depth

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the purpose of positioning pipes with the joist run?

To improve the aesthetics of the building

To save money on materials

To prevent damage to the building fabric

To make it easier to install the pipes

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Why are waste pipe systems and soil pipe systems difficult to position under floors?

Because they are fragile

Because they require large pipe sizes

Because they are heavy

Because they are expensive

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What should NOT be done when positioning waste pipe systems and soil pipe systems?

Positioning them across the joist run

Positioning them with the joist run

Notching of joists

Positioning them under floors

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?