The Agile Manifesto and Principles

The Agile Manifesto and Principles

Professional Development

16 Qs

quiz-placeholder

Similar activities

CPQ Day

CPQ Day

Professional Development

12 Qs

iPhone Xs Max & OnePlus 6T

iPhone Xs Max & OnePlus 6T

Professional Development

11 Qs

Product Quiz

Product Quiz

Professional Development

15 Qs

CPR_Quiz_Arrays and strings

CPR_Quiz_Arrays and strings

Professional Development

20 Qs

Kuis NUTRIFLAKES III

Kuis NUTRIFLAKES III

Professional Development

20 Qs

Manajemen Risiko

Manajemen Risiko

Professional Development

15 Qs

DTA Kaun Banega QuizPati - Theme: General Knowledge

DTA Kaun Banega QuizPati - Theme: General Knowledge

Professional Development

20 Qs

FA Quizz

FA Quizz

Professional Development

20 Qs

The Agile Manifesto and Principles

The Agile Manifesto and Principles

Assessment

Quiz

Professional Development

Professional Development

Practice Problem

Medium

Created by

Michael Myers

Used 13+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

16 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

____ and ____ over ____ and ____.

Individuals and interactions; processes and tools

People and communication; policies and procedures

Answer explanation

In the agile approach, Individuals and interactions are valued over processes and tools.

2.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

____ over ____.

Working software; Comprehensive documentation

Comprehensive documentation; working software

Answer explanation

In the agile approach, working software is valued over comprehensive documentation

3.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

____ over ____.

Agreed upon work; scope creep

Customer collaboration; Contract negotiation

Answer explanation

In the agile approach, customer collaboration is valued over contract negotiation

4.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

____ over ____.

Responding to change; following a plan

Follow the plan; change only when necessary

Answer explanation

In the agile approach, responding to change is valued over following a plan

5.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

Our highest priority is to________ of valuable software.

satisfy the customer through early and continuous delivery

produce the customer's order

provide a viable solution

satisfy the customer through on-time and on budget delivery

6.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

Welcome ________ even late in development. Agile processes ________ for the customer's competitive advantage.

defined requirements; reject change

changing requirements; harness change

detailed activities; open to change

evolving requirements; change daily

7.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

Deliver working software _______, from a couple of weeks to a couple of months, with a preference to the _________.

never; longer timescale

frequently; shorter timescale

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

By signing up, you agree to our Terms of Service & Privacy Policy

Already have an account?