1.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

Media Image

What is the purpose of appointing a quantity surveyor to produce a bill of quantities (BOQ)?

To reduce transparency in the tender process

To complicate the tender process

To save money on the contract price

To increase the contract price

2.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

Media Image

What are the two main types of bill of quantities (BOQ) according to NRM2 and RICS?

Firm and flexible

Approximate and accurate

Firm and approximate

Precise and estimated

3.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

Media Image

How can a bill of quantities (BOQ) help during the tender stage of a project?

By increasing the chances of overpricing by contractors

By allowing contractors to omit necessary elements

By ensuring contractors base their price on an identical list of items

By complicating the negotiation process

4.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

Media Image

What does a function bill of quantities (BOQ) allow for during the tender process?

Complication of the negotiation process

Increased chances of front loading costs by contractors

Opportunity for contractors to omit vital elements

Direct comparison between contractors and their prices

5.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

Media Image

How can a bill of quantities (BOQ) be beneficial during the construction phase?

By making variations difficult to identify

By helping to save money in case of reduced quantity price

By complicating the regular payments valuation process

By increasing the possibility of client exploitation by the contractor

6.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

Media Image

What is the purpose of having a bill of quantities (BOQ) during the post-construction phase?

To complicate the asset management process

To decrease transparency in the final accounting process

To make lifecycle estimates and maintenance cost inaccurate

To evaluate final payments at final account stage

7.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

Media Image

What is the potential benefit of having a bill of quantities (BOQ) for asset management purposes?

It can lead to inaccurate lifecycle estimates

It can complicate the maintenance cost measurement

It can act as a readily available document for asset management purposes

It can decrease transparency in the final accounting process

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?