Cold Water Systems LO2

Cold Water Systems LO2

Professional Development

13 Qs

quiz-placeholder

Similar activities

Black History Month

Black History Month

Professional Development

10 Qs

DICEST - Talent Khoj - 8-April

DICEST - Talent Khoj - 8-April

Professional Development

10 Qs

Prevent 2019-20

Prevent 2019-20

Professional Development

11 Qs

Факти про ЕС

Факти про ЕС

University - Professional Development

15 Qs

Insulin Launch Quiz

Insulin Launch Quiz

Professional Development

18 Qs

GE102 - Midterm Quiz

GE102 - Midterm Quiz

Professional Development

16 Qs

Labor Relations and Negotations 1

Labor Relations and Negotations 1

University - Professional Development

15 Qs

02. Quiz Sosialisasi

02. Quiz Sosialisasi

Professional Development

15 Qs

Cold Water Systems LO2

Cold Water Systems LO2

Assessment

Quiz

Professional Development

Professional Development

Practice Problem

Medium

Created by

George Harding

Used 608+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

13 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

When installing an incoming mains, the pipe should be laid between:

500mm and 1200mm

800mm and 1500mm

750mm and 1350mm

1000mm and 2000mm

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What colour is MDPE?

Black

Blue

Red

Yellow

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the minimum size pipe modern properties are supplied with?

15mm

22mm

25mm

28mm

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

At which point on a cold water supply system is regulated under the Water Regulations?

From the ferrule

From the water treatment plant

From the Boundary stop valve

From the stop valve inside the property

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

All meters must be installed in a chamber located at the boundary of the property.

True

False

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Due to MDPE degrading in sunlight, what is the maximum permitted length you can install above the finish floor level?

400mm

275mm

200mm

150mm

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In accordance with the Water Regulations, where should the stop valve be located?

Inside the building, below floor level, as close as possible to the door

Inside the airing cupboard, as close as possible to the door

Outside the building, as close as possible to the property boundary

Inside the building, above floor level, as close as possible to the point of entry

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?

Discover more resources for Professional Development