Midway through developing a complex software program, Alix, a senior developer, mentions that there is a slight possibility that the server that the code relies on may crash. This could cause all of the progress made in the last week to be lost. In which document should the project manager not this?
PM Guild Cup 2023F

Quiz
•
Other
•
Professional Development
•
Hard
Lcit Pmguild
FREE Resource
30 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Risk Management Plan
Risk Register
Issue Log
Resource Management Plan
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Lincy is a new project manager starting at your firm. She tells you that she has been asked to work with the team on a lessons-learned document. Lincy is not familiar with this document and asks you what should be included. Which of the following elements are you least likely to tell her to include in the lessons learned document?
The names of the individuals who were at fault and how they were reprimanded
An overview or summary of the situation
The impact of any actions that were taken to correct the situation
Updates to the project documents
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Annie has a student intern shadowing her for the day to learn about project management. Annie is discussing change management with the intern when she is asked about the project manager’s role in the change management process. Which of the following is not a responsibility of the project manager?
The project manager is responsible for assessing the impacts of proposed changes.
The project manager is responsible for approving or rejecting change requests.
The project manager is responsible for developing the change management plan.
The project manager should prevent the root causes of changes.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Your supervisor has asked you to help train a new project manager, Navneet. You are reviewing several lessons learned documents with Navneet that should help onboard her and familiarize her with the way your organization manages projects. Which of the following lessons learned represents tacit knowledge?
A Key supplier, T9 Woodworking, has upped its pricing by 15% for future projects.
The technical codebase will be outdated by 2027 and will need to be refactored by then to adhere to new database policiesGoing forward, company policy states that projects over $5M will require signature authority from the CEO..
Going forward, company policy states that projects over $5M will require signature authority from the CEO.
Arham, a senior project manager, often has a difficult time eliciting stakeholder feedback from the marketing department at your company
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The PMO at your firm has informed that under certain circumstances, a typical, competitive procurement process may not be necessary. Under which circumstances would this be the case?
Project DIS has a large budget.
The manager of project OIC is familiar with several vendors who specialize in the required services.
Project IDS has a scope component that requires a patent from a unique vendor
Project AKF requires standard woodworking skills and has a predefined scope and schedule.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Khamille is new to your consulting firm and is asking for your mentorship. She would like to know what your responsibility as a project manager is concerning project artifacts. What will you tell her?
The Project Manager is responsible for updating all project artifacts.
The Project Manager is responsible for updating all project artifacts.
The Project Manager is responsible for ensuring that project artifacts are accessible to all parties who may need them.
The Project Manager is responsible for sending out updated project artifacts to all stakeholders.
The Project Manager is responsible for composing all project artifacts.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Rima is responsible for managing the procurement for her project. Her PMO instructed her to only arrange contracts with vendors that pose a low risk for her firm. What type of contract should Rima use?
Time and materials contract
Cost Contract
Cost-reimbursable contract
Fixed Prince Contract
Create a free account and access millions of resources
Similar Resources on Quizizz
30 questions
Agilidad Empresarial

Quiz
•
Professional Development
25 questions
Sports, Sports, Sports

Quiz
•
Professional Development
25 questions
Health & Safety CSCS

Quiz
•
1st Grade - Professio...
25 questions
R3S2-VirtuQuest2024

Quiz
•
Professional Development
25 questions
PUNLA Pre-Test 2024

Quiz
•
Professional Development
25 questions
R2-VirtuQuest2024

Quiz
•
Professional Development
25 questions
Storyboard Pro Certification Review

Quiz
•
Professional Development
25 questions
Nursing Research Ethics & Research Process

Quiz
•
Professional Development
Popular Resources on Quizizz
15 questions
Multiplication Facts

Quiz
•
4th Grade
20 questions
Math Review - Grade 6

Quiz
•
6th Grade
20 questions
math review

Quiz
•
4th Grade
5 questions
capitalization in sentences

Quiz
•
5th - 8th Grade
10 questions
Juneteenth History and Significance

Interactive video
•
5th - 8th Grade
15 questions
Adding and Subtracting Fractions

Quiz
•
5th Grade
10 questions
R2H Day One Internship Expectation Review Guidelines

Quiz
•
Professional Development
12 questions
Dividing Fractions

Quiz
•
6th Grade