Critical Path Analysis Quiz

Critical Path Analysis Quiz

12th Grade

8 Qs

quiz-placeholder

Similar activities

Livestream Shopping

Livestream Shopping

KG - Professional Development

10 Qs

Porter's Five Forces Analysis

Porter's Five Forces Analysis

12th Grade

10 Qs

Business Studies Practice 5.1

Business Studies Practice 5.1

10th - 12th Grade

10 Qs

Time Management Hacks for Sales Reps Quiz

Time Management Hacks for Sales Reps Quiz

12th Grade

13 Qs

International Monetary Fund

International Monetary Fund

12th Grade

10 Qs

Entrepreneurship Quiz 2

Entrepreneurship Quiz 2

12th Grade

10 Qs

Real Estate Finance Quiz#2

Real Estate Finance Quiz#2

1st - 12th Grade

10 Qs

FUNDA Quiz

FUNDA Quiz

12th Grade

10 Qs

Critical Path Analysis Quiz

Critical Path Analysis Quiz

Assessment

Quiz

Business

12th Grade

Practice Problem

Easy

Created by

Ms Cave

Used 2+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

8 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What are network diagrams used for in critical path analysis?

Network diagrams are used to visually represent the sequence of activities and their dependencies in critical path analysis.

Network diagrams are used to calculate financial projections in critical path analysis.

Network diagrams are used to create organizational charts in critical path analysis.

Network diagrams are used to analyze market trends in critical path analysis.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is float time in project management?

Float time is the time it takes for a project to be completed

Float time in project management refers to the amount of time a task can be delayed without causing a delay to the overall project schedule.

Float time is the time allocated for team members to take breaks during the project

Float time is the time added to the project schedule to account for unexpected delays

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does EST stand for in critical path analysis?

End of Schedule Time

Emergency Stop Time

Early Start Time

Estimated Start Time

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does LFT stand for in project management?

Lemonade Flavor Test

Lowest Frequency Threshold

Longest Feasible Time

LFT stands for Late Finish Time in project management.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How is the critical path in a network diagram identified?

By identifying the longest path through the network diagram.

By randomly selecting a path in the network diagram.

By identifying the shortest path through the network diagram.

By choosing the path with the most number of nodes in the network diagram.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the purpose of critical path analysis in project management?

To track the number of meetings held during the project

To estimate the total cost of the project

To randomly assign tasks to team members

The purpose of critical path analysis in project management is to identify the longest sequence of tasks in a project, which determines the minimum time needed to complete the project.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How does float time impact the critical path of a project?

Float time only affects the critical activities

Float time has no impact on the critical path

Float time can impact the critical path by allowing flexibility in non-critical activities, which can affect the overall project duration and completion date.

Float time always extends the critical path

8.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What happens if a task on the critical path is delayed?

The project will be completed ahead of schedule

It will have no impact on the project timeline

The critical path will be redefined

If a task on the critical path is delayed, it will directly impact the overall project timeline and may cause the project to be delayed as well.