Đề 1(1-100)

Đề 1(1-100)

University

99 Qs

quiz-placeholder

Similar activities

Final Exam in LEA 1

Final Exam in LEA 1

University

100 Qs

усщтщьшсы 1-100

усщтщьшсы 1-100

University

100 Qs

MIDTERM EXAMINATION - Human Reproduction

MIDTERM EXAMINATION - Human Reproduction

University

100 Qs

Đề 3 (201-300)

Đề 3 (201-300)

University

100 Qs

Đề 2 (101-200)

Đề 2 (101-200)

University

100 Qs

Đề 7 (601-700)

Đề 7 (601-700)

University

100 Qs

NISM test 2

NISM test 2

University

99 Qs

Modulo 1 sest parte 1

Modulo 1 sest parte 1

University

99 Qs

Đề 1(1-100)

Đề 1(1-100)

Assessment

Quiz

Specialty

University

Medium

Created by

Hoàng Nam

Used 49+ times

FREE Resource

99 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

If the earned value (EV-earned value) is 350, the actual cost (AC-actual value) is 400, the planned value (PV-planned value) is 325, the cost incurred (CV-cost variation) How much is it?
350
-75
400
-50

2.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

Would a PM likely use…………… to make sure the project team knows what work is included in each of their work packages?
Project scope statement
Product range
WBS dictionary
Schedule

3.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

A PM has just been assigned to a new project and given a project vision and preliminary project scope statement. What is the first thing he should do?
Create the project scope statement
Make sure all relevant parties have input into the scope (are involved).
Project risk analysis
Begin implementing the project management plan

4.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

Your project management plan makes project schedules quite time-consuming. If the project's network diagram is unchanged but you have additional human resources, the best thing to do is:
Project promotion
Re-allocation of resources
Cancel project (crash)
Monte Carlo analysis

5.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

If project time and cost are not as important as the amount of resources used in a month, the best thing to do is to do the following:
Perform Monte Carlo analysis
Fast track the project
Implement resource balancing
Life cycle cost analysis

6.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

Early in the project, you have a discussion with the sponsor about the estimating techniques that should be used. You want an expert assessment, but the sponsor objects and wants to use a similar estimate. What's best to do?
Agree with the same estimate as an expert assessment
Suggest life cycle assessment as a compromise
Determine why the sponsor wants such an accurate estimate
Try to convince the sponsor to agree with expert assessments because they are more accurate

7.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

During activity definition, an employee determines that an activity needs to be performed. However, another employee believed that the activity was not part of the project as he understood it in the project scope statement. What is the best PM to do?
Try to build consensus within the project team
Make personal decisions
Ask the sponsor for details
Ask senior management for details

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?