Đề 4 (301-400)

Đề 4 (301-400)

University

100 Qs

quiz-placeholder

Similar activities

100 câu tiếng anh

100 câu tiếng anh

University

100 Qs

SOAL100

SOAL100

University

96 Qs

RT_4110 Exam II

RT_4110 Exam II

University

100 Qs

LEC 8+9 S1.3 (Phần 1 ) Phôi thai học đại cương (SLIDE)

LEC 8+9 S1.3 (Phần 1 ) Phôi thai học đại cương (SLIDE)

University

102 Qs

Hamilton College Family Quiz 2

Hamilton College Family Quiz 2

KG - Professional Development

100 Qs

MA clinical and lab review

MA clinical and lab review

12th Grade - University

100 Qs

JP Final Spring 2019

JP Final Spring 2019

University

100 Qs

Zach's Book 2: Second Symphony

Zach's Book 2: Second Symphony

KG - University

99 Qs

Đề 4 (301-400)

Đề 4 (301-400)

Assessment

Quiz

Specialty

University

Practice Problem

Hard

Created by

Hoàng Nam

Used 1+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

100 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

If a project has a 60% chance of earning $100,000 and a 40% chance of losing $100,000, the expected monetary value for the project is:

A. Gained $100,000
B. Loss of $60,000
C. Earned $20,000
D. Loss of $40,000

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

While planning your risk management, your team came up with 434 risks and 16 main causes of these risks. The project is the last in a series of projects on which the team will work together. The sponsor was highly motivated and a significant amount of time was invested to ensure the project charter was completed and signed by all key stakeholders. During the project planning phase, the team does not come up with an effective way to reduce or escape risk. It is not a job that can be outsourced or eliminated. The best solution is:

Take risks
Continued investigation to mitigate risks
Look for ways to avoid risks
Find ways to transfer the risk

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In which of the following contract types is the seller most involved in the scope of the project?

Fixed price contract
Cost plus fixed fee contract
Time and materials contracts
Purchase order contract

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During which part of the contracting process does contract negotiation take place?

Purchasing plan
Contract signing plan
Request seller reply
Select seller.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A PM is creating requests for proposal (RFP). What process of purchasing management is he in?

Purchasing plan
Contract signing plan
Request seller reply
Select seller.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A customer on a project tells the PM that he has run out of money to pay for the project. What should the PM do first?

A. Change the work schedule to be done later than the old schedule so that customers have more capital
B. Begin closing administrative activities
C. Stop work
D. Reducing personnel of part of the project team (release part of the team)

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Negotiations between the two parties are becoming complicated, so party A makes some notes that both parties sign. However, when the work was completed, Party B affirmed that they did not request the provision of an item that both parties agreed on during the negotiation process, because it was not included in the next contract. In this case, party B:

Not true, because both parties must comply with what they agreed to
Yes, that's why it's an offer
In general, it is true, because both parties are only required to perform what is written in the contract.
In general it is wrong, since all contracts must be respected

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?