Đề 4 (301-400)

Đề 4 (301-400)

University

100 Qs

quiz-placeholder

Similar activities

ANATOMY AND PHYSIOLOGY LAB FINAL

ANATOMY AND PHYSIOLOGY LAB FINAL

12th Grade - University

100 Qs

Unit 12 - ELT 502

Unit 12 - ELT 502

University - Professional Development

99 Qs

MIDTERM EXAMINATION - Human Reproduction

MIDTERM EXAMINATION - Human Reproduction

University

100 Qs

Modulo 1 sest parte 1

Modulo 1 sest parte 1

University

99 Qs

FINAL Exam KO32 Drug Education

FINAL Exam KO32 Drug Education

University

100 Qs

Intro to Insurance

Intro to Insurance

University - Professional Development

103 Qs

Đề 3 (201-300)

Đề 3 (201-300)

University

100 Qs

ch.7-11

ch.7-11

University

101 Qs

Đề 4 (301-400)

Đề 4 (301-400)

Assessment

Quiz

Specialty

University

Hard

Created by

Hoàng Nam

Used 1+ times

FREE Resource

100 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

If a project has a 60% chance of earning $100,000 and a 40% chance of losing $100,000, the expected monetary value for the project is:
A. Gained $100,000
B. Loss of $60,000
C. Earned $20,000
D. Loss of $40,000

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

While planning your risk management, your team came up with 434 risks and 16 main causes of these risks. The project is the last in a series of projects on which the team will work together. The sponsor was highly motivated and a significant amount of time was invested to ensure the project charter was completed and signed by all key stakeholders. During the project planning phase, the team does not come up with an effective way to reduce or escape risk. It is not a job that can be outsourced or eliminated. The best solution is:
Take risks
Continued investigation to mitigate risks
Look for ways to avoid risks
Find ways to transfer the risk

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In which of the following contract types is the seller most involved in the scope of the project?
Fixed price contract
Cost plus fixed fee contract
Time and materials contracts
Purchase order contract

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During which part of the contracting process does contract negotiation take place?
Purchasing plan
Contract signing plan
Request seller reply
Select seller.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A PM is creating requests for proposal (RFP). What process of purchasing management is he in?
Purchasing plan
Contract signing plan
Request seller reply
Select seller.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A customer on a project tells the PM that he has run out of money to pay for the project. What should the PM do first?
A. Change the work schedule to be done later than the old schedule so that customers have more capital
B. Begin closing administrative activities
C. Stop work
D. Reducing personnel of part of the project team (release part of the team)

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Negotiations between the two parties are becoming complicated, so party A makes some notes that both parties sign. However, when the work was completed, Party B affirmed that they did not request the provision of an item that both parties agreed on during the negotiation process, because it was not included in the next contract. In this case, party B:
Not true, because both parties must comply with what they agreed to
Yes, that's why it's an offer
In general, it is true, because both parties are only required to perform what is written in the contract.
In general it is wrong, since all contracts must be respected

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?