PM - Chapter 5

PM - Chapter 5

University

18 Qs

quiz-placeholder

Similar activities

NYT- Mexico

NYT- Mexico

University

15 Qs

BBA sem 2 Business Statistics

BBA sem 2 Business Statistics

University

20 Qs

Unit 3. Innovation Strategy (ITM)

Unit 3. Innovation Strategy (ITM)

University

13 Qs

Chapter 6: Information Systems/Order Processing

Chapter 6: Information Systems/Order Processing

University

20 Qs

Recruitment

Recruitment

University

15 Qs

BATTLE OF THE BRAINS

BATTLE OF THE BRAINS

11th Grade - University

20 Qs

ASPERA IRRELEVANT'22 Programme Quiz

ASPERA IRRELEVANT'22 Programme Quiz

University

20 Qs

Introduction To Accounting:

Introduction To Accounting:

11th Grade - University

13 Qs

PM - Chapter 5

PM - Chapter 5

Assessment

Quiz

Business

University

Practice Problem

Medium

Created by

Phan Trinh

Used 4+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

18 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The document that officially sanctions the project is the:

Project charter

Project plan

Feasibility study

Cost-benefit analysis

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The work breakdown structure “control points” for the management of a project are the:

Milestones

Work packages

Activities

Constraints

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

One of the most common reasons why projects undergo scope changes is:

Poor work breakdown structure

Poorly defined statement of work

Lack of resources

Lack of funding

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following generally cannot be validated using a work breakdown structure?

Schedule control

Cost control

Quality control

Risk management

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

With the work breakdown structure (WBS) shown on the right, the cost of WBS element 1.2.2.0 is:

$20K

$30K

$50K

Cannot be determined

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

With the work breakdown structure (WBS) shown on the right, the cost of WBS element 1.1.1 is:

$12K

$13K

$25K

Cannot be determined

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

With the work breakdown structure (WBS) shown on the right, the cost of the entire program (1.00.00) is:

$25K

$66K

$91K

Cannot be determined

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?