What is Earned Value (EV)?
Earn Value Management Quiz

Quiz
•
Business
•
University
•
Medium
PROFESOR ISA
Used 3+ times
FREE Resource
21 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Actual cost of work performed
Budgeted cost of work scheduled
Budgeted cost of work performed
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Explain the formula for Earned Value (EV).
EV = % complete - BAC
EV = % complete + BAC
EV = % complete / BAC
EV = % complete * BAC
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is Planned Value (PV) in Earned Value Analysis?
Actual cost of work performed
Authorized budget assigned to the work scheduled to be accomplished
Budget at Completion (BAC)
Planned cost of work performed
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Define Actual Cost (AC) in the context of Earned Value Management.
Planned cost for the work completed
Cost budgeted for the work completed
Total cost actually incurred for the work completed
Estimated cost for the work completed
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the significance of Cost Performance Index (CPI) in Earned Value Analysis?
It measures the scope of the project by comparing the actual work completed to the planned work
It measures the cost efficiency of the project by comparing the actual cost of work performed to the budgeted cost of work performed.
It measures the time efficiency of the project by comparing the actual time taken to complete the work to the estimated time
It measures the quality of the project by comparing the actual quality of work performed to the expected quality
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Explain the concept of Schedule Performance Index (SPI) in Earned Value Management.
The Schedule Performance Index (SPI) measures the quality of work in Earned Value Management.
The Schedule Performance Index (SPI) measures the cost efficiency in Earned Value Management.
The Schedule Performance Index (SPI) measures the risk management in Earned Value Management.
The Schedule Performance Index (SPI) measures the efficiency of schedule performance in Earned Value Management.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
How is Earned Value Analysis used to forecast project outcomes?
By guessing the project outcomes
By comparing planned value, earned value, and actual cost of the project
By using only the planned value
By ignoring the project data
Create a free account and access millions of resources
Similar Resources on Quizizz
20 questions
Theory of Accounts

Quiz
•
University
20 questions
IGCSE Business Studies - 5.3 Income Statements Quiz

Quiz
•
10th Grade - University
20 questions
MKT1001- Topic 1.1 and 1.2

Quiz
•
University
19 questions
BUAD 1000 Final Review_UPDATED 202340

Quiz
•
University
20 questions
Advance data-structures

Quiz
•
University
20 questions
REVISION 3 : TOPIC 3, 4, 5 & 7

Quiz
•
1st Grade - University
17 questions
PM - Chap 12

Quiz
•
University
16 questions
Accounting Vocabulary

Quiz
•
University - Professi...
Popular Resources on Quizizz
15 questions
Character Analysis

Quiz
•
4th Grade
17 questions
Chapter 12 - Doing the Right Thing

Quiz
•
9th - 12th Grade
10 questions
American Flag

Quiz
•
1st - 2nd Grade
20 questions
Reading Comprehension

Quiz
•
5th Grade
30 questions
Linear Inequalities

Quiz
•
9th - 12th Grade
20 questions
Types of Credit

Quiz
•
9th - 12th Grade
18 questions
Full S.T.E.A.M. Ahead Summer Academy Pre-Test 24-25

Quiz
•
5th Grade
14 questions
Misplaced and Dangling Modifiers

Quiz
•
6th - 8th Grade