Earn Value Management Quiz

Earn Value Management Quiz

University

21 Qs

quiz-placeholder

Similar activities

BUAD 1000 Final Review_UPDATED 202340

BUAD 1000 Final Review_UPDATED 202340

University

19 Qs

Advance data-structures

Advance data-structures

University

20 Qs

REVISION 3 : TOPIC 3, 4, 5 & 7

REVISION 3 : TOPIC 3, 4, 5 & 7

1st Grade - University

20 Qs

laagot

laagot

University

18 Qs

QUIZ 1 : TOPIC 5 [MANUFACTURING OVERHEAD]

QUIZ 1 : TOPIC 5 [MANUFACTURING OVERHEAD]

1st Grade - University

20 Qs

QUIZ 3 : TOPIC 10 [Standard Costing & Variance Analysis]

QUIZ 3 : TOPIC 10 [Standard Costing & Variance Analysis]

1st Grade - University

20 Qs

MKT1001- Topic 1.1 and 1.2

MKT1001- Topic 1.1 and 1.2

University

20 Qs

Project Management Chapter 7

Project Management Chapter 7

University - Professional Development

21 Qs

Earn Value Management Quiz

Earn Value Management Quiz

Assessment

Quiz

Business

University

Medium

Created by

PROFESOR ISA

Used 3+ times

FREE Resource

21 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is Earned Value (EV)?

Actual cost of work performed

Budgeted cost of work scheduled

Budgeted cost of work performed

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Explain the formula for Earned Value (EV).

EV = % complete - BAC

EV = % complete + BAC

EV = % complete / BAC

EV = % complete * BAC

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is Planned Value (PV) in Earned Value Analysis?

Actual cost of work performed

Authorized budget assigned to the work scheduled to be accomplished

Budget at Completion (BAC)

Planned cost of work performed

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Define Actual Cost (AC) in the context of Earned Value Management.

Planned cost for the work completed

Cost budgeted for the work completed

Total cost actually incurred for the work completed

Estimated cost for the work completed

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the significance of Cost Performance Index (CPI) in Earned Value Analysis?

It measures the scope of the project by comparing the actual work completed to the planned work

It measures the cost efficiency of the project by comparing the actual cost of work performed to the budgeted cost of work performed.

It measures the time efficiency of the project by comparing the actual time taken to complete the work to the estimated time

It measures the quality of the project by comparing the actual quality of work performed to the expected quality

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Explain the concept of Schedule Performance Index (SPI) in Earned Value Management.

The Schedule Performance Index (SPI) measures the quality of work in Earned Value Management.

The Schedule Performance Index (SPI) measures the cost efficiency in Earned Value Management.

The Schedule Performance Index (SPI) measures the risk management in Earned Value Management.

The Schedule Performance Index (SPI) measures the efficiency of schedule performance in Earned Value Management.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How is Earned Value Analysis used to forecast project outcomes?

By guessing the project outcomes

By comparing planned value, earned value, and actual cost of the project

By using only the planned value

By ignoring the project data

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?