
PMP Full Mock
Authored by Arun Prakash Sharma
Other
Professional Development
Used 73+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
175 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A project team realizes that the product's architecture will not support the growing number of users.
What should the project manager do?
Assign a team member to execute performance testing and ensure the product's performance is acceptable.
Hire external experts to assess the product architecture and come up with a resolution plan.
Engage with the product owner on the new development and prioritize the solution on the product backlog.
Negotiate with the stakeholders to slow down product development until a viable solution is available.
Answer explanation
C. Engage with the product owner on the new development and prioritize the solution on the product backlog.
The first step for the project manager will be to share this vital information with the product owner, so that business stakeholders may be invited to share their thoughts and value considerations made, then the product backlog can be reprioritized to reflect this. This sequence allows for company, team, and business stakeholder concerns to be adequately addressed.
The other answer choices are incorrect. Performance testing happens concurrently during development or at the end of the iteration/release and will not solve the identified gap but only highlight it down the road. Hiring external experts may be premature and may not be approved/available in the budget. Negotiating with the stakeholders to slow down product development until a viable solution is available may not be the best option for the company.
This question and rationale were developed in reference to:
PMBOK Guide 7th Edition (page 76 , 185, retrospectives page 127, 180)
| The Agile Practice Guide (No Date) PMI/PMI/Anex A1/ [Item Section 8 Project Quality Management]
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
During a one-year project, a team delivered everything as requested and defined by the product owner and met all of the sprint goals. The project was on track regarding schedule, scope, and budget. A few months after the project release, the product satisfaction surveys show that the customer's level of satisfaction is surprisingly low.
What should the project manager do to prevent this situation in the future?
Hold a kick-off meeting at the beginning of the project.
Improve application of test automation techniques.
Increase project management office (PMO) involvement.
Conduct periodic reviews with customer involvement.
Answer explanation
D. Conduct periodic reviews with customer involvement
The project manager should conduct periodic reviews with the customer. During the whole project, there was no real user involvement and input on the product being created. Although the team was performing well, they were not creating the 'right' product to satisfy customers.
The other answer choices are incorrect. Holding a kick-off meeting at beginning of project is not sufficient; and increasing PMO involvement and test automation do not address customer satisfaction issue.
This question and rationale were developed in reference to:
Essential Scrum: A Practical Guide to the Most Popular Agile Process (No Date) Kenneth S. Rubin//21/ [Item]
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A project manager is delivering a complex project for a client who has their own project manager. The client's project manager is the sole decision maker for the project but is not the delegated financial authority. For every financial decision, the client's project manager must seek approval from a higher authority. This additional step has caused significant impacts on resource management, cost, and time of project delivery.
How can the project manager resolve this problem?
Raise this problem in the quarterly project status report.
Add the problem to the lessons learned report.
Escalate the problem to the project steering committee.
Discuss the problem with the client's project manager.
Answer explanation
C. Escalate the problem to the project steering committee.
The steering committee is an advisory body that is made up of senior stakeholders and experts that provide guidance on a lot of different issues that could face companies and projects such as budgets, new endeavors, company policy, marketing strategies, and project management concerns. An authority issue should only be resolved by the steering committee. In this case, the project team cannot resolve this issue on their own, so the problem should be escalated.
In this case, the client's project manager is not the delegated financial authority. The client's project manager must seek approval from a higher authority for all financial decisions, which has caused significant impacts on resource management, cost, and time of project delivery. Addressing the issue with the client's project manager would not address the core issue as the client's project manager does not have the financial authority, which is causing the issue, so it must be escalated. Adding the problem to the lessons learned report is incorrect because it does not proactively address the issue. Waiting to review the issue at the next quarterly meeting/status report is inappropriate due to the significance of the impacts. The next meeting/status report may be months away and this issue is already causing significant impacts and should be addressed as soon as possible to prevent further issues.
This question and rationale were developed in reference to:
PMBOK Guide Sixth Edition (2018) PMI/PMI/2.4/42 [Item]
| Project Managers Portable HandBook, 3rd Ed (No Date) //5.4.6 Conflict Resolution Modes/ [Item]
PMBOK Guide Seventh Edition (2022) /// [2.3 FUNCTIONS ASSOCIATED WITH PROJECTS] [4.4.3 MEETINGS AND EVENTS]
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
During a software development project, the team realized that several features failed to comply with quality requirements. After receiving instructions to fix the issues, one team member becomes frustrated, claiming that unclear requirements are causing the issues. Other team members argue that negligent testing is the real cause of these issues. The testers blame poor coding quality.
What should the project manager do?
Support the project team in a retrospective to identify the root cause of the quality issues.
Remove the most frustrated resource from the team as the confusion is impacting team motivation.
Perform a quality review in each stage of the development life cycle to identify quality issues.
Discuss the issue with the management team to identify possible solutions to improve quality.
Answer explanation
A. Support the project team in a retrospective to identify the root cause of the quality issues.
The project team is initially responsible for conflict resolution, but the project manager can facilitate it when required. Retrospective meetings provide an opportunity for the project team to review how they work and to suggest changes to improve processes and efficiency. Retrospectives can be used to identify threats to performance, and project team cohesion, and to seek improvements. Facilitation helps the project team create consensus around solutions, resolve conflicts, and make decisions.
The other answer choices do not promote the same level of collaboration and problem-solving within the team and may not address the underlying issues effectively.
This question and rationale were developed in reference to:
PMBOK Guide Seventh Edition (2022) /// [2.5.1 PROJECT PROCESSES] [2.3.3 FACILITATE AND SUPPORT]
| The Project Management Tool Kit: 100 Tips and Techniques for Getting the Job Done Right (No Date) /Amazon/21/ [Item Creative Problem Solving; Training 5 is Delphi Technique ]
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A project manager has received quotes from two vendors for the same parts. Vendor A has informed the project manager that they fulfilled a similar order two months ago at a price that was 2% under the original planned cost. Vendor B has a history of on-time delivery but has announced a price increase.
How should the project manager evaluate this situation?
Review the agreements and procurement documentation for Vendor B to force them to keep the original pricing.
Evaluate the contract clauses to reduce the orders from Vendor B, and buy them from Vendor A to improve project indicators.
Use the metrics from Vendor A to request better pricing from Vendor B, keeping both providers as a risk mitigation strategy.
Review the work performance information of both vendors against their contracts to find the preferred supplier.
Answer explanation
D. Review the work performance information of both vendors against their contracts to find the preferred supplier
To evaluate the situation, the project manager should review the work performance information of both vendors against their contracts to find the preferred supplier. If the project manager decides to go for an alternative source, they must first review the vendors' past performance. The project manager should not make a decision based solely on price. They should consider a variety of factors. By reviewing the work performance information of both vendors, the project manager can gain a better understanding of their strengths and weaknesses.
The other answer choices are incorrect. It is unlikely that the project manager will be able to force Vendor B to keep the original pricing. Vendor B is within their rights to increase their prices. Reducing the orders from Vendor B may not be possible, depending on the terms of the contract. Additionally, this may damage the relationship with Vendor B. Lastly, Vendor B may not be willing to match Vendor A's pricing. Additionally, relying on a single vendor can be risky.
This question and rationale were developed in reference to:
PMBOK Guide Sixth Edition (2018) PMI/PMI/12.3.3.2/499 [Item]
| Project Management: A Systems Approach to Planning, Scheduling, and Controlling (No Date) Harold Kerzner//19.3/ [Item Location 25697]
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A project manager is concerned about delivering the planned business value because the product owner is not engaged. What should the project manager do to address the concern?
Review and update the communications management plan.
Review and update the stakeholder engagement plan.
Review and update the resource management plan.
Review and update the risk management plan.
Answer explanation
B. Review and update the stakeholder engagement plan.
The amount and effectiveness of stakeholder engagement should be monitored throughout the project. A disengaged product owner can cause negative impacts and diminish the probability of achieving intended outcomes. The project manager should review the stakeholder engagement plan and assess whether the current engagement strategy is effective or if it needs to be adjusted. Once the project manager has reviewed the stakeholder engagement plan, they can determine the root cause of the issue and make adjustments to increase engagement.
The other options are incorrect. The communications management, resource management, and risk management plans are not as effective in addressing the issue of disengagement.
This question and rationale were developed in reference to:
PMBOK Guide Seventh Edition (2022) PMI /// [2.1 STAKEHOLDER PERFORMANCE DOMAIN]
| The Agile Practice Guide (No Date) PMI/PMI/6.6.3 - An Agile PMO is multidisciplinary/82 [Item]
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
While working on a long project with many changes, a project manager is informed by a team member that some users are uncomfortable with certain product functionalities released in the previous iteration.
Which action should the project manager take?
Ensure that the team assignments are clear.
Obtain stakeholder feedback and team insights.
Communicate the changes to the team.
Update the change-log and issue log.
Answer explanation
B. Obtain stakeholder feedback and team insights.
Obtaining stakeholder feedback and team insights on each release is part of an iterative approach to development, thus the project manager should do so. This enables alignment among stakeholder needs, expectations, and project objectives.
The other answer choices are incorrect because they do not result in a change to the project and clarifying team assignments does not address the issue at hand.
This question and rationale were developed in reference to:
O'Reilly Platform (No Date) //12 - Agile coach skills/ [Item Book title: Coaching agile teams: a companion for scrum masters, agile coaches and project managers in transition ]
| The Agile Practice Guide (No Date) PMI/PMI/3/21 [Item 3.1.2]
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?