CH. 1 - Project Lifecycles

CH. 1 - Project Lifecycles

12th Grade

45 Qs

quiz-placeholder

Similar activities

Business Management Midterm Review

Business Management Midterm Review

10th - 12th Grade

50 Qs

CMASSESMENT2.01&2.02

CMASSESMENT2.01&2.02

9th - 12th Grade

46 Qs

Marketing & Entrepreneurship Final Exam 2023 Review

Marketing & Entrepreneurship Final Exam 2023 Review

12th Grade

47 Qs

ACCTG 38 MIDTERM EXAM

ACCTG 38 MIDTERM EXAM

12th Grade

45 Qs

4.01 MC Question Review - Business Essentials

4.01 MC Question Review - Business Essentials

9th - 12th Grade

40 Qs

Unit 5 HL Quesstions

Unit 5 HL Quesstions

12th Grade

40 Qs

Business Management: Chapter 20 Test Review

Business Management: Chapter 20 Test Review

9th - 12th Grade

40 Qs

Marketing - What you know so far...and some general revision

Marketing - What you know so far...and some general revision

12th Grade

45 Qs

CH. 1 - Project Lifecycles

CH. 1 - Project Lifecycles

Assessment

Quiz

Business

12th Grade

Easy

Created by

Migdalyn Vega

Used 1+ times

FREE Resource

45 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does a project lifecycle in project management refer to?

A method for calculating the total cost of a project

The sequential and iterative process through which a project progresses from initiation to completion

The final stage of a project where deliverables are handed over

A tool used for stakeholder analysis

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does a project lifecycle provide for managing and executing the project?

A set of financial resources

A risk management plan

A structured framework

A marketing strategy

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does the Iterative type of project lifecycle involve?

Dividing the project into smaller, manageable increments

Combining predictive and adaptive methods

Repeating planning, executing, and evaluating cycles

Emphasizing flexibility and continuous improvement

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which project lifecycle type emphasizes flexibility, collaboration, and continuous improvement?

Predictive

Iterative

Incremental

Adaptive (Agile)

5.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

The Hybrid type of project lifecycle combines which TWO of the following methods?

Predictive

Adaptive

SCRUM

Sprint

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is a key characteristic of the Predictive Life Cycle?

Undefined roles and responsibilities

High degree of uncertainty

No clear goals or deadlines

Defined start and end date

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which type of projects is the Predictive Life Cycle best suited for?

Projects with unclear objectives and requirements

Complex projects with expected changes

Projects with well-defined objectives and requirements

Projects that require a high degree of flexibility

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?