1.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

Media Image

While managing a project, the project manager needs to be aware of the different types of resources on a project. Equipment, materials, facilities and infrastructure would be considered what type of resources?

Team resources
Physical resources
Personnel resources
Location resources

2.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

Media Image

The organization has decided to use agile methods on their next project. How will the organization describe an agile project team?

Self organized
Project Manager Led
Organization Led
PMO Led

3.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

Media Image

To save money on a new project, the organization’s senior management has decided to use virtual teams instead of co-locating the entire project’s team. They have acquired the latest technology in audio and video conferencing. What is a potential issue that a virtual team might face? To save money on a new project, the organization’s senior management has decided to use virtual teams instead of co-locating the entire project’s team. They have acquired the latest technology in audio and video conferencing. What is a potential issue that a virtual team might face? To save money on a new project, the organization’s senior management has decided to use virtual teams instead of co-locating the entire project’s team. They have acquired the latest technology in audio and video conferencing. What is a potential issue that a virtual team might face?

Schedulling Meetings
Having a diverse set of experts
Accommodating with people with dissabilities
Feeling of isolation

4.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

Media Image

The project team is using an assignment matrix, particularly a RACI chart. What is an important rule the team should use when using a RACI chart?

Ensure that every activity has at least one responsible person
Ensure that every activity has at least one informed person
Ensure that every activity has at least one person to consulated
Ensure that every activity has at least one person who is held accountable

5.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

Media Image

The project manager has completed the resource management plan and has decided to lay out what could be considered acceptable behavior by the project team members. Where will the project manager communicate the ground rules on the project?

In the project charter
In the resource charter
In the team charter
In the project resource charter

6.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

Media Image

Which stakeholders would be the best to create the team charter?

Project Manager
Project Team
Project Sponsor
Senior Management

7.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

Media Image

Senior management and the project sponsor will hold a meeting about the current project in 2 days. They have requested a breakdown of the different resources that the project will use. What document should the project manager show during the meeting to display the resources by type?

Resource requirement
Basis of estimates
Resource Breakdown Structure
WBS

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?

Discover more resources for Professional Development