Geotechnical Report 10a

Geotechnical Report 10a

Professional Development

6 Qs

quiz-placeholder

Similar activities

Polish geography

Polish geography

1st Grade - Professional Development

10 Qs

Państwa - stolice

Państwa - stolice

Professional Development

10 Qs

The Pollution Quiz

The Pollution Quiz

2nd Grade - Professional Development

10 Qs

SG vs the World - True or False

SG vs the World - True or False

Professional Development

10 Qs

Quiz for Nerds

Quiz for Nerds

Professional Development

10 Qs

Geografi

Geografi

Professional Development

11 Qs

New Zealand

New Zealand

KG - Professional Development

10 Qs

Countries of the world 🌎

Countries of the world 🌎

KG - Professional Development

10 Qs

Geotechnical Report 10a

Geotechnical Report 10a

Assessment

Quiz

Geography

Professional Development

Practice Problem

Easy

Created by

Rob Marq

Used 13+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

6 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What type of recommendation would not typically be included in a geotechnical report?

Pavement thickness

Degree of compaction

.Height of the structure

Footing depth and width

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which item is the most important to be performed before any underground work is started?

Draw a sketch of the site.

.Have existing underground utilities located.

Decide how many boreholes you will need to drill.

Set up a pre-grade meeting.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In the Earthwork Recommendations section, which of the following type of soil or conditions was not addressed?

Rock fill

Transition pads

.Expansive soil

On-site material

None of the above

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

According to the boring and trench logs, at a depth of 1 ft or deeper in the southern portion of the site, expansive soils are expected to be encountered.

True

.False

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Cut slopes excavated into undisturbed Mehrten breccia or conglomerate should be stable if cut no steeper than 1:1.

True

.False

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Regarding fill slopes, which one of the following statements is false?

.If a keyway is placed at the toe of a 3:1 slope no benching is necessary while placing the rest of the slope fill.

Fill slopes must be built from the bottom up—not pushed out from the top.

Track walking slopes for compaction is not acceptable.

The keyway shall be a minimum of 15 ft wide and sloped downward into the slope at 2%.