CE453 Quiz 2
Quiz
•
Professional Development
•
University
•
Practice Problem
•
Hard
Rosanne Andaluz
Used 2+ times
FREE Resource
Enhance your content in a minute
50 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
Which of the following characteristics is NOT associated with a functional organization?
Each employee has one clear superior
Staff are grouped by areas of specialization
Staff are managed by a person with expertise in their area
Resources are easily shared between department and projects
2.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
Which of the following is an advantage associated with managing projects in a functional organization?
Unity of command-one clear supervisor for each worker
Combines task focus with technical capability
Each unit contains a variety of specialists suited to solving complex problems
Rapid communication between the various functions working on the project
3.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
Which of the following is a disadvantage associated with managing projects in a projectized organization?
Response times and decision making are slow
Traditional department barriers are reduced
Team members have difficulty focusing on project issues
Team members assigned to a project are often underutilized
4.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
All of the following are advantages associated with managing projects in projectized organization EXCEPT
Response times and decision making are swift
One boss-the project manager
Departmental barriers are reduced
New assignment is guaranteed after the project ends
5.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
Projectized organization often adopt which of the following techniques where project team members are physically placed close to one another to improve communications and working relationships?
Collaboration
Co-location
Coordination
Consolidation
6.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
There are five steps involved when defining a project, which of the following is the first?
Establish project priorities
Define project scope
Verify the budget available
Assign team members to work on the project
Determine the required completion date
7.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
Which of the following defined project scope?
The length of your project and how much it will cost
The deliverables or outputs during the course of the project
The range of resources you have available and their capabilities
What you expect to deliver to your customer when the project is complete
The range of customer expectations
Create a free account and access millions of resources
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?
Similar Resources on Wayground
50 questions
1° Exámen Simulacro FMENT - 2do Parcial CNEM
Quiz
•
University
48 questions
輔大教程模擬考
Quiz
•
University
46 questions
Ujian PKTI
Quiz
•
University
50 questions
Webinar Zero To Hero: Strategi Masuk PTN Tembus Skor SNBT 700+
Quiz
•
University
51 questions
Disaster Readiness Quiz
Quiz
•
9th Grade - University
50 questions
D.P.C. "EXAMEN FINAL"
Quiz
•
University
52 questions
專利與智慧財產權
Quiz
•
University
45 questions
EXAMEN SIMULACRO ÁREAS GENERALES EXANI - II, INGRESO A NORMALES
Quiz
•
University
Popular Resources on Wayground
10 questions
Honoring the Significance of Veterans Day
Interactive video
•
6th - 10th Grade
9 questions
FOREST Community of Caring
Lesson
•
1st - 5th Grade
10 questions
Exploring Veterans Day: Facts and Celebrations for Kids
Interactive video
•
6th - 10th Grade
19 questions
Veterans Day
Quiz
•
5th Grade
14 questions
General Technology Use Quiz
Quiz
•
8th Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
15 questions
Circuits, Light Energy, and Forces
Quiz
•
5th Grade
19 questions
Thanksgiving Trivia
Quiz
•
6th Grade