1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is NOT listed as an excusable delay?

Force Majeure

Owner's delays

Compensation

Contractor's delays

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is NOT a reason for which the Contract Time may be extended?

An act or neglect by the Owner or Architect

Changes orders in the Work

Gc's or sub's caused delays

Adverse weather conditions documented in accordance with Section 15.1.6.2

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What should be confirmed about the impact of a storm on a project's timeline?

It is shorter than the direct impact of the storm.

It is equal to the direct impact of the storm.

It is likely to be longer than the direct impact of the storm.

It has no effect on the project's timeline.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is a consequence of failing to complete before the Contract Time?

Penalty in the amount of the retainage.

No consequences.

Liquidated Damages

Extension of the Contract Time.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is NOT a reason for default termination of work?

Contractor is far behind

Work fails to meet quality requirements

Contractor is financially insolvent

Contractor completes the work ahead of schedule

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is a convenience termination?

Termination due to contractor's failure to meet deadlines

Termination for no specific reason and includes final payment to contractor

Termination due to contractor's financial insolvency

Termination due to work not meeting the quality requirements

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What clause do the Contractor and Owner contract waives claims against each other for non-direct costs?

Waiver of compensatory damages

Waiver of consequential damages

Waiver of incidental damages

Waiver of punitive damages

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?