Chapt 6

Quiz
•
Professional Development
•
1st Grade
•
Hard
WS Ho
Used 1+ times
FREE Resource
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
If earned value (EV) = 350, actual cost (AC) = 400, and planned value (PV) = 325, what is cost
variance (CV)?
A. 350
B. -75
C. 400
D. -50
2.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
Estimate at completion (EAC) is a periodic evaluation of:
A. The cost of work completed.
B. The value of work performed
C. The anticipated total cost at project completion
D. What it will cost to finish the project.
3.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
Which of the following is NOT needed in order to come up with a project estimate?
A. A WBS
B. A network diagram
C. Risks
D. Change requests
4.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
A rough order of magnitude estimate is made during which project management process group?
Planning
Closing
Executing
Initiating
5.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
Cost performance measurement is BEST done through which of the following?
A. Asking for a percent complete from each team member and reporting that in the monthly progress report
B. Calculating earned value and using the indexes and other calculations to report past
performance and forecast future performance
C. Using the 50/50 rule and making sure the life cycle cost is less than the project cost
D. Focusing on the amount expended last month and what will be expended the following month
6.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
Project setup costs are an example of:
A. Variable costs.
B. Fixed costs.
C. Overhead costs
D. Opportunity costs
7.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
Your cost forecast shows that you will have a cost overrun at the end of the project. Which of the following should you do?
Eliminate risks in estimates and re-estimate
Meet with the sponsor to find out what work can be done sooner
Cut quality
Decrease scope
Create a free account and access millions of resources
Similar Resources on Wayground
10 questions
Chapt4

Quiz
•
1st Grade
13 questions
PMI-SH Plan and Manage Quality of Products/deliverables

Quiz
•
1st Grade
10 questions
ECM566 Construction Project Management

Quiz
•
1st Grade
11 questions
PMI-SH Assess and Manage Risks

Quiz
•
1st Grade
14 questions
RMP - 6. MONITOR & CLOSE RISK

Quiz
•
1st Grade
10 questions
HELLO FM III STUDENTS

Quiz
•
1st - 10th Grade
7 questions
PMBoK - PROCUREMENT

Quiz
•
1st - 12th Grade
13 questions
RMP - 1. INTRODUCTION

Quiz
•
1st Grade
Popular Resources on Wayground
18 questions
Writing Launch Day 1

Lesson
•
3rd Grade
11 questions
Hallway & Bathroom Expectations

Quiz
•
6th - 8th Grade
11 questions
Standard Response Protocol

Quiz
•
6th - 8th Grade
40 questions
Algebra Review Topics

Quiz
•
9th - 12th Grade
4 questions
Exit Ticket 7/29

Quiz
•
8th Grade
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
19 questions
Handbook Overview

Lesson
•
9th - 12th Grade
20 questions
Subject-Verb Agreement

Quiz
•
9th Grade