Chapt 6

Chapt 6

1st Grade

10 Qs

quiz-placeholder

Similar activities

DCQ6262-QUIZ2(JUN2020)

DCQ6262-QUIZ2(JUN2020)

1st - 10th Grade

10 Qs

IFRS - Are we good to go - W4 - IAS 23 Borrowing cost

IFRS - Are we good to go - W4 - IAS 23 Borrowing cost

1st - 3rd Grade

10 Qs

04. Integration Management

04. Integration Management

1st Grade

12 Qs

PMI-SH Plan and Manage Quality of Products/deliverables

PMI-SH Plan and Manage Quality of Products/deliverables

1st Grade

13 Qs

ECM566 Construction Project Management

ECM566 Construction Project Management

1st Grade

10 Qs

PM Quiz

PM Quiz

1st - 10th Grade

10 Qs

Logistics

Logistics

1st - 3rd Grade

11 Qs

RMP - 6. MONITOR & CLOSE RISK

RMP - 6. MONITOR & CLOSE RISK

1st Grade

14 Qs

Chapt 6

Chapt 6

Assessment

Quiz

Professional Development

1st Grade

Hard

Created by

WS Ho

Used 1+ times

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

If earned value (EV) = 350, actual cost (AC) = 400, and planned value (PV) = 325, what is cost

variance (CV)?

A. 350

B. -75

C. 400

D. -50

2.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Estimate at completion (EAC) is a periodic evaluation of:

A. The cost of work completed.

B. The value of work performed

C. The anticipated total cost at project completion

D. What it will cost to finish the project.

3.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Which of the following is NOT needed in order to come up with a project estimate?

A. A WBS

B. A network diagram

C. Risks

D. Change requests

4.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

A rough order of magnitude estimate is made during which project management process group?

Planning

Closing

Executing

Initiating

5.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Cost performance measurement is BEST done through which of the following?

A. Asking for a percent complete from each team member and reporting that in the monthly progress report

B. Calculating earned value and using the indexes and other calculations to report past

performance and forecast future performance

C. Using the 50/50 rule and making sure the life cycle cost is less than the project cost

D. Focusing on the amount expended last month and what will be expended the following month

6.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Project setup costs are an example of:

A. Variable costs.

B. Fixed costs.

C. Overhead costs

D. Opportunity costs

7.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Your cost forecast shows that you will have a cost overrun at the end of the project. Which of the following should you do?

Eliminate risks in estimates and re-estimate

Meet with the sponsor to find out what work can be done sooner

Cut quality

Decrease scope

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?