Chapt 6

Chapt 6

1st Grade

10 Qs

quiz-placeholder

Similar activities

Gujarat State

Gujarat State

KG - Professional Development

10 Qs

Pre Test PPKB PEDAGOGIK 2

Pre Test PPKB PEDAGOGIK 2

1st Grade

15 Qs

11. Risk Management

11. Risk Management

1st - 3rd Grade

12 Qs

Past Simple

Past Simple

KG - 9th Grade

10 Qs

England Quiz of the Week (Week 1)

England Quiz of the Week (Week 1)

1st - 12th Grade

12 Qs

Blended Learning Models

Blended Learning Models

KG - University

11 Qs

Test your Chromebook Knowledge!

Test your Chromebook Knowledge!

KG - 12th Grade

11 Qs

Pre- Read - OVH

Pre- Read - OVH

1st - 3rd Grade

10 Qs

Chapt 6

Chapt 6

Assessment

Quiz

Professional Development

1st Grade

Practice Problem

Hard

Created by

WS Ho

Used 1+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

If earned value (EV) = 350, actual cost (AC) = 400, and planned value (PV) = 325, what is cost

variance (CV)?

A. 350

B. -75

C. 400

D. -50

2.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Estimate at completion (EAC) is a periodic evaluation of:

A. The cost of work completed.

B. The value of work performed

C. The anticipated total cost at project completion

D. What it will cost to finish the project.

3.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Which of the following is NOT needed in order to come up with a project estimate?

A. A WBS

B. A network diagram

C. Risks

D. Change requests

4.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

A rough order of magnitude estimate is made during which project management process group?

Planning

Closing

Executing

Initiating

5.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Cost performance measurement is BEST done through which of the following?

A. Asking for a percent complete from each team member and reporting that in the monthly progress report

B. Calculating earned value and using the indexes and other calculations to report past

performance and forecast future performance

C. Using the 50/50 rule and making sure the life cycle cost is less than the project cost

D. Focusing on the amount expended last month and what will be expended the following month

6.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Project setup costs are an example of:

A. Variable costs.

B. Fixed costs.

C. Overhead costs

D. Opportunity costs

7.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Your cost forecast shows that you will have a cost overrun at the end of the project. Which of the following should you do?

Eliminate risks in estimates and re-estimate

Meet with the sponsor to find out what work can be done sooner

Cut quality

Decrease scope

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?