Search Header Logo

Chapt 6

Authored by WS Ho

Professional Development

1st Grade

Used 1+ times

Chapt 6
AI

AI Actions

Add similar questions

Adjust reading levels

Convert to real-world scenario

Translate activity

More...

    Content View

    Student View

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

If earned value (EV) = 350, actual cost (AC) = 400, and planned value (PV) = 325, what is cost

variance (CV)?

A. 350

B. -75

C. 400

D. -50

2.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Estimate at completion (EAC) is a periodic evaluation of:

A. The cost of work completed.

B. The value of work performed

C. The anticipated total cost at project completion

D. What it will cost to finish the project.

3.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Which of the following is NOT needed in order to come up with a project estimate?

A. A WBS

B. A network diagram

C. Risks

D. Change requests

4.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

A rough order of magnitude estimate is made during which project management process group?

Planning

Closing

Executing

Initiating

5.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Cost performance measurement is BEST done through which of the following?

A. Asking for a percent complete from each team member and reporting that in the monthly progress report

B. Calculating earned value and using the indexes and other calculations to report past

performance and forecast future performance

C. Using the 50/50 rule and making sure the life cycle cost is less than the project cost

D. Focusing on the amount expended last month and what will be expended the following month

6.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Project setup costs are an example of:

A. Variable costs.

B. Fixed costs.

C. Overhead costs

D. Opportunity costs

7.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Your cost forecast shows that you will have a cost overrun at the end of the project. Which of the following should you do?

Eliminate risks in estimates and re-estimate

Meet with the sponsor to find out what work can be done sooner

Cut quality

Decrease scope

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?