Schedule (Chapter 6)
Quiz
•
Life Project
•
Professional Development
•
Practice Problem
•
Medium
Asma Budi Aswadi
Used 5+ times
FREE Resource
Enhance your content in a minute
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
You are constructing a school building and due to some unforeseen incidents, your project is delayed. To bring the project on schedule, you are thinking about running several activities in parallel which were earlier planned to run sequentially. So, you started reviewing activities such as excavation of foundation, building walls, carpentry work, electrical work, and plumbing work, etc. After the review, you decide to run the carpentry, electrical, and plumbing works together. Excavating the foundation for the construction of a wall is an example of which of the following?
Mandatory dependency
Discretionary dependency
External dependency
Internal dependency
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
You have two activities with Finish to Start sequences. The duration of the first activity is 10 days, and the duration of the second activity is 8 days. The estimated time completed for these activities is 18 days. The client asks you complete these activities within 15 days; you review his request and agree to do so at no extra cost. Now, you plan to start the second activity three days before the first activity completes so that both activities can be completed in 15 days. This process is known as:
Schedule modification
Fast tracking
Crashing
None of the above
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
In your project, you have two activities, D and E. These two activities have a common successor, Activity F. Activity D will be completed on the 10th day and activity E will be completed on the 15th day. Therefore, Activity D can be delayed by 5 days without affecting the early start of Activity F.
This delay is known as:
Total float
Free float
Project buffers
Feeding buffer
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
The client has given you a project to construct a cold storage plant. Everything was going as planned, however, due to some unforeseen incidents, your project is delayed. The client is in a hurry and has threatened you with a large penalty if you are not able to complete the project on time. So, you started working hard to complete the project and avoid the fine. You are working overtime, bringing in more resources from other projects, and renting extra equipment; finally, you complete the project on time. This is an example of:
Resource smoothing
Fast tracking
Crashing
Resource leveling
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Following is an illustration of a project network activity node that includes some information about activity B. Assuming that the work starts on day one (not day zero) and given the information provided, what is the late start of activity B?
35
36
37
39
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
During initiating phase of your project, as a Project Manager, was required by the organization to pay attention to the required resources and duration of each activity in your project. Afterward, you compiled the result along with the logical sequence to become your project schedule and completed it with schedule data and potential day off in your project. What you should do next?
Get approval for the project schedule
Distribute the project schedule to all project team member
Re-review your Project Charter
Assess potential risk from the schedule developed
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
You are the project manager of a construction company. You know that the builders start painting the walls 30 days after they start installing the drywall. This waiting time can also be referred to as:
Lead time
Project float
Constraint
Lag
Create a free account and access millions of resources
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
Popular Resources on Wayground
5 questions
This is not a...winter edition (Drawing game)
Quiz
•
1st - 5th Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
10 questions
Identify Iconic Christmas Movie Scenes
Interactive video
•
6th - 10th Grade
20 questions
Christmas Trivia
Quiz
•
6th - 8th Grade
18 questions
Kids Christmas Trivia
Quiz
•
KG - 5th Grade
11 questions
How well do you know your Christmas Characters?
Lesson
•
3rd Grade
14 questions
Christmas Trivia
Quiz
•
5th Grade
20 questions
How the Grinch Stole Christmas
Quiz
•
5th Grade
Discover more resources for Life Project
26 questions
Christmas Movie Trivia
Lesson
•
8th Grade - Professio...
25 questions
Christmas Movies
Quiz
•
Professional Development
20 questions
Christmas Trivia
Quiz
•
Professional Development
15 questions
Fun Holiday Trivia
Quiz
•
Professional Development
25 questions
Name That Tune - Christmas
Quiz
•
Professional Development
29 questions
Christmas Song Emoji Pictionary
Quiz
•
Professional Development
9 questions
Holiday Movie Trivia
Lesson
•
Professional Development
34 questions
Winter Trivia
Quiz
•
Professional Development
