Schedule (Chapter 6)

Schedule (Chapter 6)

Professional Development

10 Qs

quiz-placeholder

Similar activities

Revealing Revelation Chapter 13 Quiz

Revealing Revelation Chapter 13 Quiz

Professional Development

10 Qs

Who knows me best?

Who knows me best?

Professional Development

15 Qs

Bendy Quiz

Bendy Quiz

Professional Development

10 Qs

Adam & Helen

Adam & Helen

Professional Development

11 Qs

Mindset Mastery: Self-Care and Growth

Mindset Mastery: Self-Care and Growth

Professional Development

8 Qs

Ai viết CV đỉnh nhất?

Ai viết CV đỉnh nhất?

Professional Development

6 Qs

ShweNote Questions

ShweNote Questions

Professional Development

10 Qs

NSW HWS

NSW HWS

Professional Development

12 Qs

Schedule (Chapter 6)

Schedule (Chapter 6)

Assessment

Quiz

Life Project

Professional Development

Practice Problem

Medium

Created by

Asma Budi Aswadi

Used 5+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

You are constructing a school building and due to some unforeseen incidents, your project is delayed. To bring the project on schedule, you are thinking about running several activities in parallel which were earlier planned to run sequentially. So, you started reviewing activities such as excavation of foundation, building walls, carpentry work, electrical work, and plumbing work, etc. After the review, you decide to run the carpentry, electrical, and plumbing works together. Excavating the foundation for the construction of a wall is an example of which of the following?

Mandatory dependency

Discretionary dependency

External dependency

Internal dependency

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

You have two activities with Finish to Start sequences. The duration of the first activity is 10 days, and the duration of the second activity is 8 days. The estimated time completed for these activities is 18 days. The client asks you complete these activities within 15 days; you review his request and agree to do so at no extra cost. Now, you plan to start the second activity three days before the first activity completes so that both activities can be completed in 15 days. This process is known as:

Schedule modification

Fast tracking

Crashing

None of the above

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

In your project, you have two activities, D and E. These two activities have a common successor, Activity F. Activity D will be completed on the 10th day and activity E will be completed on the 15th day. Therefore, Activity D can be delayed by 5 days without affecting the early start of Activity F.

This delay is known as:

Total float

Free float

Project buffers

Feeding buffer

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The client has given you a project to construct a cold storage plant. Everything was going as planned, however, due to some unforeseen incidents, your project is delayed. The client is in a hurry and has threatened you with a large penalty if you are not able to complete the project on time. So, you started working hard to complete the project and avoid the fine. You are working overtime, bringing in more resources from other projects, and renting extra equipment; finally, you complete the project on time. This is an example of:

Resource smoothing

Fast tracking

Crashing

Resource leveling

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Media Image

Following is an illustration of a project network activity node that includes some information about activity B. Assuming that the work starts on day one (not day zero) and given the information provided, what is the late start of activity B?

35

36

37

39

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

During initiating phase of your project, as a Project Manager, was required by the organization to pay attention to the required resources and duration of each activity in your project. Afterward, you compiled the result along with the logical sequence to become your project schedule and completed it with schedule data and potential day off in your project. What you should do next?

Get approval for the project schedule

Distribute the project schedule to all project team member

Re-review your Project Charter

Assess potential risk from the schedule developed

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

You are the project manager of a construction company. You know that the builders start painting the walls 30 days after they start installing the drywall. This waiting time can also be referred to as:

Lead time

Project float

Constraint

Lag

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?