Scheduling

Scheduling

Professional Development

7 Qs

quiz-placeholder

Similar activities

PROCESO INTEGRAL TMI CON MASS 2.0

PROCESO INTEGRAL TMI CON MASS 2.0

Professional Development

7 Qs

LocalizeBook Quiz - What is LocalizeBook

LocalizeBook Quiz - What is LocalizeBook

Professional Development

9 Qs

AI in Business

AI in Business

Professional Development

10 Qs

MB / Stellar - Quiz

MB / Stellar - Quiz

Professional Development

10 Qs

MTSS Reading CFU

MTSS Reading CFU

Professional Development

8 Qs

Accounting terms

Accounting terms

Professional Development

8 Qs

EPIC

EPIC

Professional Development

10 Qs

U 22

U 22

Professional Development

10 Qs

Scheduling

Scheduling

Assessment

Quiz

Business

Professional Development

Hard

Created by

Luis Cunha

FREE Resource

7 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

When utilizing backward scheduling in SAP Operation orders, what information is required to initiate the process?

Start date of the production order

Resource availability and capacity

End date of the production order

Quantity of materials required

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How does backward scheduling impact the planning of individual operations within an Operation order?

Operations are scheduled from start to end

Operations are scheduled based on resource availability

Operations are scheduled from end to start

Operations are scheduled simultaneously

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Why is scheduling essential for efficient production planning in SAP?

To create graphical representations of workflows

To synchronize production with market trends

To manage financial transactions

To avoid resource conflicts and bottlenecks

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the primary purpose of defining intra-operations in SAP routings?

To track the movement of raw materials

To optimize communication between different production orders

To manage activities that occur within a single operation step

To prioritize maintenance tasks

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Where are intra-operations located?

Work Center

BOM

Routings

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does lead time scheduling in SAP consider for exact start/end dates?

Machine availability

Operation duration in the routing

Material availability

Vendor lead times

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does determination of basic dates in SAP rely on?

Work center capacity

Material master data

Operation priorities

External procurement lead times