Project Management Unit 3

Project Management Unit 3

12th Grade

46 Qs

quiz-placeholder

Similar activities

S&I Fall EOS

S&I Fall EOS

11th - 12th Grade

41 Qs

Taxes & Income Unit Test

Taxes & Income Unit Test

10th - 12th Grade

44 Qs

Admin Support EOP Review

Admin Support EOP Review

12th Grade

42 Qs

Finance Section 3 Test

Finance Section 3 Test

9th Grade - University

50 Qs

PKWU Wirausaha Produk Kerajinan untuk Pasar Lokal kelas XII

PKWU Wirausaha Produk Kerajinan untuk Pasar Lokal kelas XII

12th Grade

50 Qs

Accounting Chapter 1 Starting a Proprietorship

Accounting Chapter 1 Starting a Proprietorship

9th - 12th Grade

42 Qs

Topic 3 Accounting Cycles

Topic 3 Accounting Cycles

1st Grade - University

50 Qs

Tort Law

Tort Law

10th - 12th Grade

50 Qs

Project Management Unit 3

Project Management Unit 3

Assessment

Quiz

Business

12th Grade

Practice Problem

Hard

Created by

Isabelle Karis

Used 4+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

46 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

An activity:

is the result of completing one or more schedules

is a distinct, scheduled portion of work performed during the course of a project

is always on the critical path

is the combination of all scheduled events that define a project

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Scheduling is:

the conversion of a project action plan into an operating timetable

the graphical representation of the logical relationships among the project activities and events

the path through the project where, if any activity is delayed, the project is delayed

the management tool to guide the project manager and the team in planning their work

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The top-down approach for estimating resources works well when:

faced with a brand new, first-of-its-kind project

the work from above will flow to the lower levels

it has a clearly defined scope

the project manager can contemplate all details up front without detail

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The bottom-up approach for estimating resources works well when:

there is not a lot of data to work with

you do not have a lot of time

the whole team can participate and contribute

it is difficult to determine the logical sequence of the tasks

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In estimating the resources, why is it advisable to review resource availability?

Some of the needed project resources might not be present in your company.

Executives may want all work done inside the company to protect trade secrets.

Union contracts require special holidays.

Equipment may be better to purchase than rent.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Network logic diagrams in project management are a visual representation of a project's

budget.

technical requirements.

schedule.

scope.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Activity lists, with their durations, can be shown on a

Gantt chart.

calendar.

daily report.

spreadsheet.

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?