Construction Contracts Quiz

Construction Contracts Quiz

University

10 Qs

quiz-placeholder

Similar activities

Qlassic in construction

Qlassic in construction

University

10 Qs

National Building Code Chapter 3 & 4

National Building Code Chapter 3 & 4

University

10 Qs

Spec 1_Quiz 2

Spec 1_Quiz 2

University

15 Qs

FBC: Introduction to FBC

FBC: Introduction to FBC

University

12 Qs

Standard of Professional Practice

Standard of Professional Practice

University

10 Qs

Quiz on Quantity Surveying

Quiz on Quantity Surveying

University

10 Qs

L: SET 0

L: SET 0

University - Professional Development

10 Qs

SBEQ2523 DELAY & EOT

SBEQ2523 DELAY & EOT

University

15 Qs

Construction Contracts Quiz

Construction Contracts Quiz

Assessment

Quiz

Architecture

University

Hard

Created by

David Sawyer

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is a Lump Sum Contract in construction?

A contract where payment is made based on time spent rather than a fixed price.

A contract where the contractor agrees to complete the project for a specified, fixed price.

A contract that allows for payment adjustments based on actual costs of materials and labor.

A contract where payment is made in installments based on project milestones.

Answer explanation

A Lump Sum Contract in construction is a contract where the contractor agrees to complete the project for a specified, fixed price.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which type of construction contract is most beneficial for a project where the scope is not well defined?

Lump Sum Contract

Cost Plus Contract

Unit Price Contract

Time and Material Contract

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does a "Change Order" in a construction contract typically signify?

A document that terminates the contract.

A formal decision to continue the project without changes.

A modification to the contract terms, including project scope, price, or time.

A request for additional funds without changing the contract terms.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a Guaranteed Maximum Price (GMP) contract, who benefits if the project costs less than the agreed maximum price?

The contractor benefits by receiving the full GMP amount.

The owner benefits by paying only the actual costs, which are less than the GMP.

Both the owner and the contractor share the savings.

The government benefits through taxes on the saved amount.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the primary purpose of a Performance Bond in construction contracts?

To ensure that subcontractors are paid for their work.

To guarantee the quality of materials used in construction.

To protect the owner against losses due to the contractor's failure to complete the project.

To cover the cost of construction materials.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which contract type places the most risk on the contractor?

Cost Plus Contract

Lump Sum Contract

Time and Material Contract

Guaranteed Maximum Price Contract

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the main advantage of a Unit Price Contract?

It provides flexibility in adjusting the project scope.

It guarantees a fixed price for the project.

It is the simplest form of contract.

It allows for faster project completion.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?