Preconstruction Activities Quiz

Preconstruction Activities Quiz

12th Grade

12 Qs

quiz-placeholder

Similar activities

Building Laws Quiz 2- PD 1096

Building Laws Quiz 2- PD 1096

KG - Professional Development

15 Qs

Prelim, Prime Cost, Prov Sum and Pro Rata

Prelim, Prime Cost, Prov Sum and Pro Rata

9th Grade - University

10 Qs

3D Printing in Home Construction

3D Printing in Home Construction

12th Grade

10 Qs

Cost Estimating Theory

Cost Estimating Theory

12th Grade - University

16 Qs

Civil Engineering Bridge Construction Quiz

Civil Engineering Bridge Construction Quiz

12th Grade

15 Qs

Unit 9 Christmas Quiz

Unit 9 Christmas Quiz

11th - 12th Grade

16 Qs

Building Materials: Lumber

Building Materials: Lumber

10th - 12th Grade

10 Qs

Lines Used in Architectural Drawing

Lines Used in Architectural Drawing

9th - 12th Grade

10 Qs

Preconstruction Activities Quiz

Preconstruction Activities Quiz

Assessment

Quiz

Architecture

12th Grade

Hard

Created by

David Sawyer

FREE Resource

12 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the primary purpose of conducting a site investigation before starting a construction project?

To decide the color scheme of the building

To determine the best location for vending machines

To assess the soil condition and identify any potential challenges

To meet the local residents

Answer explanation

The primary purpose of conducting a site investigation before starting a construction project is to assess the soil condition and identify any potential challenges, such as unstable ground or environmental concerns.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is NOT typically a part of the permitting process for construction?

Obtaining a building permit

Securing an environmental clearance

Registering the construction workers

Getting a permit for water usage

Answer explanation

Registering the construction workers is NOT typically a part of the permitting process for construction. The other options, such as obtaining a building permit, securing an environmental clearance, and getting a permit for water usage, are commonly required during the permitting process.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Why is budgeting and cost estimation crucial in preconstruction?

It helps in advertising the project

It determines the project's financial feasibility and sets a financial plan

It is only necessary for large projects

It is a legal requirement

Answer explanation

Budgeting and cost estimation in preconstruction are crucial as they determine the project's financial feasibility and set a financial plan for its execution.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the significance of scheduling and timeline management in construction projects?

It ensures that the project finishes on time, within budget, and meets quality standards

It is only necessary for projects in cold climates

It is a formality that does not impact the project

It helps in choosing the construction materials

Answer explanation

Scheduling and timeline management in construction projects ensure the project finishes on time, within budget, and meets quality standards.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is NOT a factor in material procurement for a construction project?

Color preferences of the project manager

Availability of materials

Cost of materials

Delivery timelines

Answer explanation

Color preferences of the project manager is not a factor in material procurement for a construction project as it does not impact the quality or availability of materials.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the purpose of conducting a risk assessment during the preconstruction phase?

To increase the project cost

To identify and mitigate potential risks to the project's success

To decide the number of workers needed

To choose the construction equipment

Answer explanation

Conducting a risk assessment during the preconstruction phase helps to identify and mitigate potential risks to the project's success, ensuring a smoother project execution.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is a critical component of site investigation?

Checking the weather forecast for the next week

Soil testing for bearing capacity

Deciding on the interior decor

Surveying the nearest coffee shops

Answer explanation

Soil testing for bearing capacity is a critical component of site investigation as it helps determine the ability of the soil to support a structure.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?