Preferred AC and 125VDC
Authored by Jeff Weyhmiller
Science
Professional Development
Used 3+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
15 mins • 1 pt
The plant is at full power with Station Battery Chargers #3 and #4 in service. The #2 DC Bus Tie Breaker 72-20 fails open. Which answer below describes the condition of Preferred AC Bus loads?
Inverter #2 is powered by Battery Charger #4, Inverter #4 is powered by Station Battery #2
Inverter #4 is powered by Battery Charger #4, Inverter #2 is powered by Station Battery #2
Both Inverter #2 and Inverter #4 are powered by Battery Charger #4
Both Inverter #2 and Inverter #4 are powered by Station Battery #2
2.
MULTIPLE CHOICE QUESTION
15 mins • 1 pt
In the event of a power interruption, the Y-50 ABT will switch from its normal power supply to the backup power supply in less than ____, and when powered is restored to its normal power supply it will switch back in approximately _____
5 seconds
5 minutes
1 second
5 seconds
5 seconds
1 minute
1 second
5 minutes
3.
MULTIPLE CHOICE QUESTION
15 mins • 1 pt
Battery Chargers #1 and #2 are in service with the plant at full power. DC Bus #1 Tie Breaker 72-10 fails open. Shortly afterward and with 72-10 still open, a Loss of Offsite Power (LOOP) occurs. Assuming all equipment functions as expected, describe the effect on Buses 1C and 1D.
EDG 1-1 starts and loads Bus 1C. Bus 1D is deenergized.
EDG 1-2 starts and loads Bus 1D. Bus 1C is deenergized.
EDG 1-1 starts and loads Bus 1C. EDG 1-2 starts and loads Bus 1D.
Bus 1C is deenergized. Bus 1D is deenergized.
4.
MULTIPLE CHOICE QUESTION
15 mins • 1 pt
What is the effect on the Emergency Diesel Generator System as a result of a loss of DC Bus 21A?
The ability of the 1-1 EDG to automatically start and sequence loads onto Bus 1C would be lost
All diesel
protection and control for the 1-1 EDG would be lost
The ability of the 1-2 EDG to automatically start and sequence loads onto Bus 1D would be lost
All diesel
protection and control for the 1-2 EDG would be lost
5.
MULTIPLE CHOICE QUESTION
15 mins • 1 pt
(SRO ONLY)
Electrical Maintenance performs a surveillance on Station Battery #1. They report the following:
One battery cell @2.06V, all remaining cells @2.14V
Average specific gravity of 1.203 for all connected cells
Which Tech Spec 3.8.6 Action(s) is/are applicable?
(You may use ONLY the first two pages of TS 3.8.6 as a reference. You may NOT use Table 3.8.6-1)
3.8.6.A only
3.8.6.B only
3.8.6.A and 3.8.6.B
No Tech Spec actions apply
6.
MULTIPLE CHOICE QUESTION
15 mins • 1 pt
What are the power supplies for P-18A and P-18B, Fuel Oil Transfer Pumps?
P-18A: MCC-1
P-18B: MCC-8
P-18A: MCC-8
P-18B: MCC-1
P-18A: MCC-2
P-18B: MCC-1
P-18A: MCC-1
P-18B: MCC-2
7.
MULTIPLE CHOICE QUESTION
15 mins • 1 pt
An NPO returns from performing shiftly rounds and reports the following parameters for the 1-1 EDG and for the Fuel Oil Transfer System:
Jacket Water Temperature: 190°F
Lube Oil Temperature: 195°F
Air Start Tank Pressure: 220 psig
P-18B, Fuel Oil Transfer Pump, is NOT aligned for automatic operation
What are the Tech Spec implications of these parameters? You may use T.S 3.8.1 and 3.8.3 as references.
Tech Spec Required Action 3.8.1.B is not met
Tech Spec Required Action 3.8.3.D is not met
Tech Spec Required Action 3.8.1.B is not met.
Tech Spec Required Action 3.8.3.D is not met
No Tech Spec Required Actions not met
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
10 questions
Earth Day Trivia Quiz
Quiz
•
Professional Development
11 questions
6.1 Chopper
Quiz
•
Professional Development
14 questions
Quiz sobre Redes Industriales II
Quiz
•
Professional Development
14 questions
Quiz sobre Infraestructura de Red
Quiz
•
Professional Development
5 questions
El profesional Tecsup
Quiz
•
Professional Development
Popular Resources on Wayground
15 questions
Fractions on a Number Line
Quiz
•
3rd Grade
10 questions
Probability Practice
Quiz
•
4th Grade
15 questions
Probability on Number LIne
Quiz
•
4th Grade
20 questions
Equivalent Fractions
Quiz
•
3rd Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
22 questions
fractions
Quiz
•
3rd Grade
6 questions
Appropriate Chromebook Usage
Lesson
•
7th Grade
10 questions
Greek Bases tele and phon
Quiz
•
6th - 8th Grade
Discover more resources for Science
20 questions
Black History Month Trivia Game #1
Quiz
•
Professional Development
20 questions
90s Cartoons
Quiz
•
Professional Development
12 questions
Mardi Gras Trivia
Quiz
•
Professional Development
7 questions
Copy of G5_U5_L14_22-23
Lesson
•
KG - Professional Dev...
12 questions
Unit 5: Puerto Rico W1
Quiz
•
Professional Development
42 questions
LOTE_SPN2 5WEEK2 Day 4 We They Actividad 3
Quiz
•
Professional Development
15 questions
Balance Equations Hangers
Quiz
•
Professional Development
31 questions
Servsafe Food Manager Practice Test 2021- Part 1
Quiz
•
9th Grade - Professio...