Project Management Quiz Scope

Project Management Quiz Scope

Professional Development

19 Qs

quiz-placeholder

Similar activities

Change Management

Change Management

Professional Development

15 Qs

Future Heroes

Future Heroes

Professional Development

18 Qs

Requirement

Requirement

Professional Development

14 Qs

PMI-ACP Quiz01

PMI-ACP Quiz01

Professional Development

15 Qs

Introduction to Project Management Quiz

Introduction to Project Management Quiz

Professional Development

15 Qs

UiPath

UiPath

Professional Development

14 Qs

Project Management Quiz

Project Management Quiz

Professional Development

15 Qs

PM fundamentals

PM fundamentals

Professional Development

16 Qs

Project Management Quiz Scope

Project Management Quiz Scope

Assessment

Quiz

Other

Professional Development

Hard

Created by

Citizen TV

FREE Resource

19 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

An organization's value chain can be represented by a special type of flowchart called SIPOC. SIPOC stands for:

Superior service, inferior service, peak hour service, optimized service, and client service

Simple, intellectual, procedural, optimal coding

Sample, information, practice, organization, and control

Suppliers, inputs, process, outputs, and customers

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Verified deliverables are inputs in which of the following scope management processes?

Define Scope

Create WBS

Validate Scope

Control Scope

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which of the following processes produces a work breakdown structure as an output?

Create WBS

Define Scope

Develop Project Management Plan

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

All of the following are true regarding the Control Scope process EXCEPT:

It assures that underlying causes of all requested changes and recommended corrective actions are understood and processed through the Integrated Change Control process

One of the key focuses in the process may be dispute resolution related to project scope

It monitors the status of the project and product scope, maintains control over the project by preventing overwhelming scope change requests, and manages changes to the scope baseline

It verifies the correctness of work results

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A project manager, managing a data center project, had the opportunity to attend several meetings about the project prior to the creation of the project charter. In one of the meetings, the sponsor specifically denied funding for two very specific items. Two months into the project, a couple of stakeholders requested the project manager add work for one of the items that was strongly denied by the sponsor. What will be the best thing the project manager can do in this situation?

Add the work if it does not have much impact on the schedule

Inform the stakeholders that the work cannot be added

Evaluate the impact of adding the work on time, cost, quality, risk, human resource, and other elements

Immediately inform the sponsor about the request that was denied by him

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Completion of the product scope is measured against which one of the following?

Scope statement

Project requirements

Project objectives

Product requirements

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Your company, ITProConsultancy, has assigned you as the project manager to upgrade the call center in your organization. The number of calls the customer support agents have to answer each month has increased drastically in the last five months, and the phone system is approaching the maximum load limit. Your team has worked on the requirements document and the project scope statement, and you are now ready to create the WBS with the help of your team members. All of the following are true regarding the WBS EXCEPT:

The WBS represents all the work required to be completed in the project

Each level of the WBS represents a verifiable product or results

Activities in the WBS should be arranged in the proper sequence they will be performed

The WBS should be decomposed to a level called the work package level where cost and schedule can easily be calculated

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?