9 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
A project team is working closely with the product owner in order to determine inputs for the scope. Due to the complexity of the project, the team will develop a hierarchical description of the project requirements in order to deliver the expected business value. Which artifact will be developed?
Risk breakdown structure (RBS)
Definition of done (DoD)
Return on investment (ROI)
Work breakdown structure (WBS)
2.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
A project manager is preparing to meet with three crucial project stakeholders on a new project. Which tools and techniques can the project manager use to capture stakeholder interest?
Review stakeholder register and meeting
Data analysis and communication skills
Data gathering and data analysis
Communication skills and cultural awareness
3.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
What process group establishes project scope, refines objectives, and defines the actions necessary to attain project objectives?
Executing
Planning
Initiating
Monitoring and Controlling
4.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
Which process involves monitoring the status of the project to update the project costs and managing changes to the cost baseline?
Estimate Costs
Control Costs
Determine Budget
Plan Cost Management
5.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
Which input may influence quality assurance work and should be monitored within the context of a system for configuration management?
Work performance data
Project documents
Scope baseline
Requirements documentation
6.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
Payback period, return on investment, internal rate of return, discounted cash flow, and net present value are all examples of:
Expert judgment.
Analytical techniques.
Earned value management.
Group decision-making techniques.
7.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
Which tool or technique is used in the Develop Project Management Plan process?
Executing
Performance reporting
SWOT analysis
Expert judgment
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?