A power system has a maximum load of 15 MW. Annual load factor is 50%. The reserve capacity of plant is _____ if the plant capacity factor is 40%.

3.75 MW

7.75 MW

46.75 MW

8.75 MW

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The area under the load curve represents ____________

maximum demand

load factor

the average load on power system

number of units generated

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The ratio of maximum demand to connected load is

Demand factor

Load factor

Utilisation Factor

Plant capacity factor

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A higher load factor means

Cost/unit is less

Less variation in load

Generation is more

All of these

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Turbine speed governing system consists of

Flyball speed governor

Hydraulic amplifier and Linkage mechanism

Speed changer

All of above

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a power plant, reserve generating capacity which is not in operation but can be made available for service is ______

Hot Reserve

Spinning Reserve

Cold Reserve

Firm power

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Time constant of turbine is lies between

0.2 to 2.5 sec

0 to 1 sec

1 to 2 sec

Depends on turbine design

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email