Đề TM2012 trên istqb.org

Quiz
•
Other
•
Professional Development
•
Easy
Nhung Dương
Used 4+ times
FREE Resource
56 questions
Show all answers
1.
MULTIPLE SELECT QUESTION
10 mins • 1 pt
Answer explanation
a) Is not correct. TDD starts with unit test case design; in agile processes, normally there are no detailed design specifications
b) Is correct. 30% of performance issues are reported in relationship to web services. These (or some of them) may be due to undefined SLA
c) Is not correct. There is no integration test level
d) Is not correct. Unit testing is under the hood of development
e) Is correct. Performance. Tests must be conducted; system not stable before day 10
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Answer explanation
a) Correct
1) Performance tests with maximum allowed response time 10 seconds for up to 10,000 simultaneous requests of user story US 03-20 are missing
2) A test condition for user story US 02-20 is missing
b) Is not correct
c) Is not correct
d) Is not correct
3.
MULTIPLE SELECT QUESTION
10 mins • 1 pt
A. Test design and test execution is outsourced
B. Test basis is changing frequently
C. Domain experts are available for consultation during test design
D. Test basis is of low quality
E. Test conditions are used for management milestone presentations
Answer explanation
a) Is correct. Questions at test design to refine coarse grained test conditions would be expensive to answer
b) Is not correct. Detailed test conditions would be hard to maintain (Syllabus)
c) Is not correct. Questions at test design to refine coarse grained test conditions could be answered by domain experts
d) Is correct. Specifying detailed test conditions could act in place of a poor test basis and contribute to defect prevention
e) Is not correct. Management does not general require that level of detail
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A. Click rapidly on company enrollment button to see what happens
B. Click on URL for our home page, check that home page displays
C. Click on company enrollment button; verify that you go to that company’s enrollment page
D.Click on company enrollment button; verify that you go to our home page
Answer explanation
a) Is not correct. Might cover this risk item, but it is a negative test and does not contain an expected result; it’s a good exploratory negative test for this risk item, though
b) Is not correct. Is a perfectly good positive logical test but does not cover the risk item
c) Is correct. Has the input to occur, the correct expected result per the scenario, and relates to the risk item
d) Is not correct. Has the wrong expected result and so it Is not correct
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A. This risk item should be assessed as a very high impact level risk
B. The test cases associated with this risk item must be run first in the test execution period
C. The test cases associated with this risk item must be run toward the middle of the test execution period
D. A large number of test cases should be associated with this risk item, based on impact
Answer explanation
a) Is correct. This risk relates to the core functionality of the application
b) Is not correct. Tests with very high impact and higher likelihood should run before this test c) Is not correct. Is not certainly true because we do not know how this risk item relates to other risk items
d) Is not correct. Is not certainly true because we do not know how effort allocation is determined based on combined impact and likelihood
6.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
A. The test sequencing is certainly incorrect since test 02.010 is higher risk than 02.019
B. If the test plan calls for running at least one test for each requirement as early as possible, the test sequencing might be correct
C. The test manager should stop test execution while evaluating all problems that exist with test sequencing
D. Running test 02.019 was a waste of time, because it did not find any defects
E. The test team might not be following the test strategy since test 02.010 is higher risk than 02.019
Answer explanation
a) Is not correct. The situation in option B, or perhaps simply blockage of tests, can explain running tests out of risk order
b) Is correct. 02.019 covers a different requirement than 02.010
c) Is not correct. While evaluating problems with test sequencing makes sense, there is no need to stop running tests while doing so
d) Is not correct. Finding defects is not the only objective of testing
e) Is correct. Higher-risk tests precede lower-risk tests in risk-based testing strategies
7.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
Câu 7: Which of the following metrics are best suited to be included in a test progress report for unit test execution?
Select TWO options.
A. Defect detection percentage (DDP) of unit test
Planned versus actual defects reported
Unit test time vs. integration test time
Number of test conditions identified
Planned versus actual coverage achieved
Answer explanation
a) Is not correct. Could not be measured timely
b) Is correct. From syllabus
c) Is not correct. Could not be measured timely
d) Is not correct. Related to test analysis progress
e) Is correct. From syllabus
Create a free account and access millions of resources
Similar Resources on Quizizz
60 questions
Java Programming Quiz

Quiz
•
Professional Development
51 questions
TEST blanc

Quiz
•
Professional Development
51 questions
PM Midterm 2022-2023

Quiz
•
Professional Development
51 questions
NDI Block 8 Study

Quiz
•
Professional Development
60 questions
PETRARCA D4 SAFARI pract cap 3-5

Quiz
•
Professional Development
55 questions
final exam study(drivers ed)

Quiz
•
10th Grade - Professi...
60 questions
ADAM Section 4

Quiz
•
Professional Development
60 questions
18th edition complete mock 5

Quiz
•
Professional Development
Popular Resources on Quizizz
15 questions
Character Analysis

Quiz
•
4th Grade
17 questions
Chapter 12 - Doing the Right Thing

Quiz
•
9th - 12th Grade
10 questions
American Flag

Quiz
•
1st - 2nd Grade
20 questions
Reading Comprehension

Quiz
•
5th Grade
30 questions
Linear Inequalities

Quiz
•
9th - 12th Grade
20 questions
Types of Credit

Quiz
•
9th - 12th Grade
18 questions
Full S.T.E.A.M. Ahead Summer Academy Pre-Test 24-25

Quiz
•
5th Grade
14 questions
Misplaced and Dangling Modifiers

Quiz
•
6th - 8th Grade