Master Scheduling (MPR)

Master Scheduling (MPR)

1st - 5th Grade

20 Qs

quiz-placeholder

Similar activities

improper Fractions

improper Fractions

4th - 6th Grade

15 Qs

Revision chapter 1

Revision chapter 1

KG - 1st Grade

18 Qs

Symbol Practice

Symbol Practice

1st Grade

15 Qs

Addition up to 100 (21.05.2021)

Addition up to 100 (21.05.2021)

1st - 2nd Grade

20 Qs

Bar Model Flip Book

Bar Model Flip Book

3rd - 4th Grade

18 Qs

TN Ready Review #3 - Fractions and Decimals

TN Ready Review #3 - Fractions and Decimals

5th - 6th Grade

15 Qs

Ratio and Proportion

Ratio and Proportion

5th Grade

20 Qs

thematic

thematic

4th Grade

20 Qs

Master Scheduling (MPR)

Master Scheduling (MPR)

Assessment

Quiz

Mathematics

1st - 5th Grade

Practice Problem

Hard

Created by

Công Lâm

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

20 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

The MPS in a make to order company has a short promise lead time and long manufacturing lead times. Which of the following would be true of such a system?

An MPS derived from a forecast on the long term horizon

A mix of actual demand and forecast would generate requirements in the mid-term horizon

Actual customer demand would provide the requirements in the short-term

All of the choices are correct

Answer explanation

Because customer orders are not far enough into the future to plan capacity needs, some forecast of demand would be required.

2.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Which of the following is not a change that can be made to the Master Schedule for the time horizon beyond the cumulative lead time?

All changes caused by poor quality

Any change caused by poor inventory accuracy

Any change having a major impact on capacity

All changes caused by bill of material changes

Answer explanation

The only problem to the MPS beyond cumulative lead time of a product is an impact on capacity. The master scheduler would require notification if large orders were booked which caused any major capacity constraints.

3.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

In a make-to-stock company, which of the following situations would not occur?

Customer orders pulled from finished goods inventory

Products exist in inventory, waiting for purchase

An MPS stated in end items

Products made to customer order

Answer explanation

Products are pulled from finished goods inventory in a make-to-stock company instead of being produced to customer order. As such, end item is the statement format for the MPS.

4.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Which of the following is a negative aspect of the chase strategy in production planning?

Capacity utilization will fluctuate

Production levels will fluctuate with sales

Resource usage will remain stable

Inventory will remain stable

Answer explanation

When the production levels fluctuate, labor, capacity usage, equipment usage, and other resource usage will fluctuate as well. Positively however, inventory will remain stable.

5.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

The Final Assembly Schedule is best defined as which of the following?

It is the same as the Master Production Schedule

It is an anticipated build schedule

It is the same as available to promise

It is the actual build schedule

Answer explanation

Subject to change, the MPS is the anticipated build schedule while the FAS is the actual build schedule and is committed to as late as possible.

6.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Which of the following is not an effect of the level strategy of production planning?

Production occurs at exactly the same rate as the sales forecast for each period

Inventory will generally build

The capacity usage remains stable

The labor force remains stable

Answer explanation

When the level strategy is applied, the production rate is stable and fluctuations in demand are absorbed by inventory.

7.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Which of the following effects are results of a company having an overloaded master schedule?

Two effects will occur, delivery performance erosion and the decrease of cost per unit due to high utilization

Two effects will occur, delivery performance will erode as well as work-in-process growing

A single effect of delivery performance eroding will occur

A single effect of cost per unit decreasing due to high utilization will occur

Answer explanation

While the cost per unit produced may decrease in a cost accounting sense, the actual costs will reduce the profit due to inefficiency of work-in- process, longer lead times, and possibly lost business.

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?