1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

You need to select a project Management approach for your team.

Key considerations include:

- The team has worked on similar projects.

- The deliverable must comply with standards and regulations

- The project task are well-defined

- The project deliverable is clearly defined.

What project management approach should you choose?

Incremental

Adaptive

Predictive

Scrum

2.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

Which scenario demonstrates a schedule dependency?

Team members must wait to start a task until after another task is completed

   Team members must schedule activities during business hours

  Team members must work independently on tasks

  Team members must determine the minimum time necessary to complete a project.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which project document authorizes the project manager to begin working on a project?

Project Charter

Project Scope Statement

Project communication plan

Project management plan

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

 

In a project, what describes work that should be included and work that should be excluded?

Work breakdown structure (WBS)

Business Case

Project baseline

Scope statement

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is a key characteristic of the adaptive project management approach?

Minimal changes due to familiarity with project requirements.

Sequential completion of tasks with no change in scope

Delivery of the product after the final phase has been completed.

Continuous refinement of the product based upon stakeholder feedback.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

  While working on your current project, the team learned a new creative approach to managing project resources.

What is a benefit of reporting this new approach in the lessons learned documentation?

To inform the client of the new approach

To inform competitors of the new approach

To inform project teams of the new approach

To inform the legal team of the new approach.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

You provide the following information to your boss 

·         Work planned vs. work completed

·         Budget planned vs. budget spent

·         Issue or roadblocks

Which type of communication are you providing

A business plan

A status update

A project charter

A contingency plan

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?